Riverside Avenue Grade Separation

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Riverside
Zip Code 92506
 
Senate District
31
Assembly District 61
Congressional District 41
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail/Highway At-Grade Crossings Eliminated  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Riverside Phillip Hannawi (951) 826-5706   phannawi@riversideca.gov
Design (PS&E) Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
Right of Way Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
Construction Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$8,500 $1,564 $10,064
Non-bond Funding
State/Federal*
$0 $14,527 $14,527
Local**
$9,013 $-1,820 $7,193
 
Total**** $17,513 $14,271 $31,784

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$500 $547 $1,047 $1,047 $1,047 $-0
Design(PS&E)
$2,000 $-547 $1,453 $1,560 $1,560 $-107
Right of Way
$13 $6,879 $6,892 $5,540 $5,540 $1,352
Construction
$15,000 $7,392 $22,392 $20,697 $20,697 $1,695
 
Total* $17,513 $14,271 $31,784 $28,844 $28,844 $2,940

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2008 

06/01/2009 
 

12/06/2012 
02/01/2008 

07/01/2012 
100  02/01/2008 

07/01/2010 


24 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2009 

03/01/2011 
12/06/2012 

12/06/2012 
07/01/2010 

04/01/2013 
100  07/01/2010 

07/01/2013 


-3 
Begin Right of Way Phase

End Right of Way Phase
06/01/2009 

03/01/2011 
12/06/2012 

12/06/2012 
07/01/2010 

12/31/2012 
100  07/01/2010 

01/10/2013 


Begin Construction Phase

End Construction Phase
12/01/2011 

06/01/2013 
12/06/2012 

12/06/2012 
10/01/2013 

04/01/2015 
100  12/03/2013 

03/25/2016 
-2 

-12 
Begin Closeout Phase

End Closeout Phase
06/01/2013 

12/01/2013 
12/06/2012 

 
04/30/2015 

10/31/2015 
75  03/25/2016 

07/31/2023 
-11 

-94 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail/Highway At-Grade Crossings Eliminated 1

Bond Funding Cost
Adopted:
$8,500,000
Current Approved:
$10,064,000
Actual Expenditures:
$10,063,100

 

Status as of December 31, 2023.