Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Riverside Avenue Grade Separation |
Description: Construct Grade Separation
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside |
City | Riverside |
Zip Code | 92506 |
Senate District |
31 |
Assembly District | 61 |
Congressional District | 41 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail/Highway At-Grade Crossings Eliminated | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Riverside | Phillip Hannawi | (951) 826-5706 | phannawi@riversideca.gov | |
Design (PS&E) Phase |
City of Riverside | Farshid Mohammadi | (951) 826-5515 | fmohammadi@riversideca.gov | |
Right of Way Phase |
City of Riverside | Farshid Mohammadi | (951) 826-5515 | fmohammadi@riversideca.gov | |
Construction Phase |
City of Riverside | Farshid Mohammadi | (951) 826-5515 | fmohammadi@riversideca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$8,500 | $1,564 | $10,064 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $14,527 | $14,527 | ||||
Local** |
$9,013 | $-1,820 | $7,193 | ||||
Total**** | $17,513 | $14,271 | $31,784 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$500 | $547 | $1,047 | $1,047 | $1,047 | $-0 | |
Design(PS&E) |
$2,000 | $-547 | $1,453 | $1,560 | $1,560 | $-107 | |
Right of Way |
$13 | $6,879 | $6,892 | $5,540 | $5,540 | $1,352 | |
Construction |
$15,000 | $7,392 | $22,392 | $20,697 | $20,697 | $1,695 | |
Total* | $17,513 | $14,271 | $31,784 | $28,844 | $28,844 | $2,940 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
02/01/2008 06/01/2009 |
12/06/2012 |
02/01/2008 07/01/2012 |
100 | 02/01/2008 07/01/2010 |
0 24 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2009 03/01/2011 |
12/06/2012 12/06/2012 |
07/01/2010 04/01/2013 |
100 | 07/01/2010 07/01/2013 |
0 -3 |
Begin Right of Way Phase
End Right of Way Phase |
06/01/2009 03/01/2011 |
12/06/2012 12/06/2012 |
07/01/2010 12/31/2012 |
100 | 07/01/2010 01/10/2013 |
0 0 |
Begin Construction Phase
End Construction Phase |
12/01/2011 06/01/2013 |
12/06/2012 12/06/2012 |
10/01/2013 04/01/2015 |
100 | 12/03/2013 03/25/2016 |
-2 -12 |
Begin Closeout Phase
End Closeout Phase |
06/01/2013 12/01/2013 |
12/06/2012 |
04/30/2015 10/31/2015 |
75 | 03/25/2016 07/31/2023 |
-11 -94 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail/Highway At-Grade Crossings Eliminated | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$8,500,000 |
Current Approved: |
$10,064,000 |
Actual Expenditures: |
$10,063,100 |
Status as of December 31, 2023.