Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 04C0007 - BALD HILLS RD & KLAMATH RIVER |
Description: Bridge No. 04C0007 - BALD HILLS RD & KLAMATH RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Humboldt County |
City | |
Zip Code | 95546 |
Senate District |
02 |
Assembly District | 01 |
Congressional District | 01 |
Caltrans District |
01 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Humboldt County | Tony Seghetti | (707) 445-7448 | tseghetti@co.humboldt.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$1,488 | $-830 | $658 | ||||
Non-bond Funding | |||||||
State/Federal* |
$12,122 | $-6,476 | $5,646 | ||||
Local** |
$60 | $11 | $71 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $13,670 | $-7,295 | $6,375 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$700 | $-61 | $639 | $645 | $645 | $-6 | |
Right of Way |
$20 | $0 | $20 | $0 | $0 | $20 | |
Construction |
$12,950 | $-7,234 | $5,716 | $5,662 | $5,662 | $54 | |
Total* | $13,670 | $-7,295 | $6,375 | $6,307 | $6,307 | $68 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
11/30/2005 10/30/2007 |
|
11/30/2005 10/30/2007 |
100 | 11/30/2005 10/30/2007 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/30/2007 02/28/2009 |
|
11/30/2007 02/28/2009 |
100 | 11/30/2007 12/25/2010 |
0 -22 |
Begin Right of Way Phase
End Right of Way Phase |
07/30/2008 01/30/2009 |
10/15/2009 10/15/2009 |
07/30/2008 01/30/2009 |
100 | 07/30/2008 04/07/2010 |
0 -14 |
Begin Construction Phase
End Construction Phase |
06/30/2009 04/30/2010 |
|
05/24/2011 05/31/2014 |
100 | 06/13/2011 03/07/2014 |
-1 3 |
Begin Closeout Phase
End Closeout Phase |
10/30/2010 |
|
06/01/2014 |
100 | 03/10/2014 01/18/2019 |
3 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$1,487,659 |
Current Approved: |
$655,572 |
Actual Expenditures: |
$649,334 |
Status as of December 31, 2023.