Caltrans Logo

Bridge No. 04C0007 - BALD HILLS RD & KLAMATH RIVER

Description: Bridge No. 04C0007 - BALD HILLS RD & KLAMATH RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Humboldt County
City
Zip Code 95546
 
Senate District
02
Assembly District 01
Congressional District 01
 
Caltrans District
01
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Humboldt County Tony Seghetti (707) 445-7448   tseghetti@co.humboldt.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$1,488 $-830 $658
Non-bond Funding
State/Federal*
$12,122 $-6,476 $5,646
Local**
$60 $11 $71
Private***
$0 $0 $0
 
Total**** $13,670 $-7,295 $6,375

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$700 $-61 $639 $645 $645 $-6
Right of Way
$20 $0 $20 $0 $0 $20
Construction
$12,950 $-7,234 $5,716 $5,662 $5,662 $54
 
Total* $13,670 $-7,295 $6,375 $6,307 $6,307 $68

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
11/30/2005 

10/30/2007 
 

 
11/30/2005 

10/30/2007 
100  11/30/2005 

10/30/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/30/2007 

02/28/2009 
 

 
11/30/2007 

02/28/2009 
100  11/30/2007 

12/25/2010 


-22 
Begin Right of Way Phase

End Right of Way Phase
07/30/2008 

01/30/2009 
10/15/2009 

10/15/2009 
07/30/2008 

01/30/2009 
100  07/30/2008 

04/07/2010 


-14 
Begin Construction Phase

End Construction Phase
06/30/2009 

04/30/2010 
 

 
05/24/2011 

05/31/2014 
100  06/13/2011 

03/07/2014 
-1 

Begin Closeout Phase

End Closeout Phase
10/30/2010 

 
 

 
06/01/2014 

 
100  03/10/2014 

01/18/2019 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$1,487,659
Current Approved:
$655,572
Actual Expenditures:
$649,334

 

Status as of December 31, 2023.