Bridge No. 04C0055 - MATTOLE RD(HNYDEW) & MATTOLE RIVER (HONEYDEW)

Description: Bridge No. 04C0055 - MATTOLE RD(HNYDEW) & MATTOLE RIVER (HONEYDEW) - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Humboldt County
City
Zip Code 95542
 
Senate District
02
Assembly District 01
Congressional District 01
 
Caltrans District
01
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Humboldt County Tony Seghetti (707) 445-7448   tseghetti@co.humboldt.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$692 $-680 $11
Non-bond Funding
State/Federal*
$5,958 $12,295 $18,253
Local**
$0 $2,353 $2,353
Private***
$0 $0 $0
 
Total**** $6,650 $13,968 $20,618

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$620 $2,378 $2,998 $2,904 $2,954 $44
Right of Way
$30 $21 $51 $25 $36 $15
Construction
$6,000 $11,569 $17,569 $0 $20,708 $-3,139
 
Total* $6,650 $13,968 $20,618 $2,929 $23,698 $-3,080

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/30/1994 

09/30/1998 
 

 
09/30/1994 

09/30/1998 
100  09/30/1994 

09/30/1998 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/2000 

09/30/2011 
 

 
09/30/2000 

01/31/2023 
100  09/30/2000 

01/31/2023 


Begin Right of Way Phase

End Right of Way Phase
09/30/2008 

09/30/2010 
 

 
07/31/2021 

12/31/2022 
100  02/16/2022 

09/01/2022 
-7 

Begin Construction Phase

End Construction Phase
06/30/2011 

04/30/2012 
 

 
05/31/2023 

12/31/2025 
04/09/2024 

12/31/2026 
-10 

-12 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

09/30/2027 
12/31/2026 

12/31/2027 


-3 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.