Bridge No. 04C0055 - MATTOLE RD(HNYDEW) & MATTOLE RIVER (HONEYDEW) |
Description: Bridge No. 04C0055 - MATTOLE RD(HNYDEW) & MATTOLE RIVER (HONEYDEW) - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Humboldt County |
City | |
Zip Code | 95542 |
Senate District |
02 |
Assembly District | 01 |
Congressional District | 01 |
Caltrans District |
01 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Humboldt County | Tony Seghetti | (707) 445-7448 | tseghetti@co.humboldt.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$692 | $-680 | $11 | ||||
Non-bond Funding | |||||||
State/Federal* |
$5,958 | $12,295 | $18,253 | ||||
Local** |
$0 | $2,353 | $2,353 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $6,650 | $13,968 | $20,618 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$620 | $2,378 | $2,998 | $2,904 | $2,954 | $44 | |
Right of Way |
$30 | $21 | $51 | $25 | $36 | $15 | |
Construction |
$6,000 | $11,569 | $17,569 | $0 | $20,708 | $-3,139 | |
Total* | $6,650 | $13,968 | $20,618 | $2,929 | $23,698 | $-3,080 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/30/1994 09/30/1998 |
|
09/30/1994 09/30/1998 |
100 | 09/30/1994 09/30/1998 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/30/2000 09/30/2011 |
|
09/30/2000 01/31/2023 |
100 | 09/30/2000 01/31/2023 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
09/30/2008 09/30/2010 |
|
07/31/2021 12/31/2022 |
100 | 02/16/2022 09/01/2022 |
-7 4 |
Begin Construction Phase
End Construction Phase |
06/30/2011 04/30/2012 |
|
05/31/2023 12/31/2025 |
0 | 04/09/2024 12/31/2026 |
-10 -12 |
Begin Closeout Phase
End Closeout Phase |
|
|
09/30/2027 |
0 | 12/31/2026 12/31/2027 |
0 -3 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.