Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 04C0207 - WILLIAMS CREEK RD & WILLIAMS CREEK |
Description: Bridge No. 04C0207 - WILLIAMS CREEK RD & WILLIAMS CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Humboldt County |
City | |
Zip Code | 95536 |
Senate District |
02 |
Assembly District | 01 |
Congressional District | 01 |
Caltrans District |
01 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Humboldt County | Tony Seghetti | (707)445-7377 | tseghetti@co.humboldt.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$115 | $25 | $140 | ||||
Non-bond Funding | |||||||
State/Federal* |
$967 | $154 | $1,121 | ||||
Local** |
$2 | $0 | $2 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,084 | $179 | $1,264 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$80 | $0 | $80 | $218 | $218 | $-138 | |
Right of Way |
$4 | $31 | $35 | $35 | $35 | $0 | |
Construction |
$1,000 | $148 | $1,148 | $1,436 | $1,436 | $-288 | |
Total* | $1,084 | $179 | $1,264 | $1,690 | $1,690 | $-426 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/30/1994 09/30/1998 |
|
09/30/1990 09/30/1998 |
100 | 09/30/1990 09/30/1998 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/30/2000 09/30/2010 |
|
09/30/2000 09/30/2009 |
100 | 08/31/1999 09/10/2010 |
13 -11 |
Begin Right of Way Phase
End Right of Way Phase |
09/30/2008 09/30/2009 |
10/15/2009 10/15/2009 |
10/30/2009 04/01/2010 |
100 | 09/10/2010 05/16/2011 |
-10 -14 |
Begin Construction Phase
End Construction Phase |
06/30/2010 04/30/2011 |
03/01/2010 03/01/2011 |
04/30/2011 09/30/2011 |
100 | 08/22/2011 03/01/2013 |
-4 -17 |
Begin Closeout Phase
End Closeout Phase |
10/30/2011 |
|
10/30/2011 |
100 | 03/01/2013 10/10/2013 |
-16 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$114,700 |
Current Approved: |
$130,651 |
Actual Expenditures: |
$140,080 |
Status as of December 31, 2023.