Caltrans Logo

Bridge No. 04C0207 - WILLIAMS CREEK RD & WILLIAMS CREEK

Description: Bridge No. 04C0207 - WILLIAMS CREEK RD & WILLIAMS CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Humboldt County
City
Zip Code 95536
 
Senate District
02
Assembly District 01
Congressional District 01
 
Caltrans District
01
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Humboldt County Tony Seghetti (707)445-7377   tseghetti@co.humboldt.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$115 $25 $140
Non-bond Funding
State/Federal*
$967 $154 $1,121
Local**
$2 $0 $2
Private***
$0 $0 $0
 
Total**** $1,084 $179 $1,264

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$80 $0 $80 $218 $218 $-138
Right of Way
$4 $31 $35 $35 $35 $0
Construction
$1,000 $148 $1,148 $1,436 $1,436 $-288
 
Total* $1,084 $179 $1,264 $1,690 $1,690 $-426

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/30/1994 

09/30/1998 
 

 
09/30/1990 

09/30/1998 
100  09/30/1990 

09/30/1998 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/2000 

09/30/2010 
 

 
09/30/2000 

09/30/2009 
100  08/31/1999 

09/10/2010 
13 

-11 
Begin Right of Way Phase

End Right of Way Phase
09/30/2008 

09/30/2009 
10/15/2009 

10/15/2009 
10/30/2009 

04/01/2010 
100  09/10/2010 

05/16/2011 
-10 

-14 
Begin Construction Phase

End Construction Phase
06/30/2010 

04/30/2011 
03/01/2010 

03/01/2011 
04/30/2011 

09/30/2011 
100  08/22/2011 

03/01/2013 
-4 

-17 
Begin Closeout Phase

End Closeout Phase
10/30/2011 

 
 

 
10/30/2011 

 
100  03/01/2013 

10/10/2013 
-16 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$114,700
Current Approved:
$130,651
Actual Expenditures:
$140,080

 

Status as of December 31, 2023.