Bridge No. 06C0108L - CYPRESS AVE WB & SACRAMENTO RIVER |
Description: Bridge No. 06C0108L - CYPRESS AVE WB & SACRAMENTO RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Shasta County |
City | Redding |
Zip Code | 96001 |
Senate District |
04 |
Assembly District | 02 |
Congressional District | 02 |
Caltrans District |
02 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Redding | James Triantafyllou | (530) 245-7232 | jtriantafyllou@ci.redding.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$115 | $0 | $115 | ||||
Non-bond Funding | |||||||
State/Federal* |
$885 | $0 | $885 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,000 | $0 | $1,000 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,000 | $0 | $1,000 | $1,000 | $1,000 | $0 | |
Total* | $1,000 | $0 | $1,000 | $1,000 | $1,000 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/18/2002 06/18/2002 |
|
01/18/2002 06/18/2002 |
100 | 01/18/2002 06/18/2002 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/16/1993 11/01/2006 |
|
04/16/1993 11/01/2006 |
100 | 04/16/1993 11/01/2006 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
11/02/2005 11/01/2006 |
|
11/02/2005 11/01/2006 |
100 | 11/02/2005 11/01/2006 |
0 0 |
Begin Construction Phase
End Construction Phase |
12/30/2006 11/30/2009 |
10/15/2009 10/15/2009 |
04/01/2007 12/31/2010 |
100 | 04/01/2007 12/31/2010 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
05/30/2010 |
|
05/30/2010 |
100 | 03/03/2011 |
-9 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$114,700 |
Current Approved: |
$114,700 |
Actual Expenditures: |
$114,700 |
Status as of December 31, 2023.