Bridge No. 08C0008 - EVERGREEN RD & COTTONWOOD CREEK

Description: Bridge No. 08C0008 - EVERGREEN RD & COTTONWOOD CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tehama County
City
Zip Code 96022
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Tehama County Gary Antone (530) 385-1462   red@tcpw.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$700 $-700 $0
Non-bond Funding
State/Federal*
$6,138 $-6,138 $0
Local**
$95 $-95 $0
Private***
$0 $0 $0
 
Total**** $6,933 $-6,933 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$828 $-828 $0 $548 $1,512 $-1,512
Right of Way
$105 $-105 $0 $0 $424 $-424
Construction
$6,000 $-6,000 $0 $0 $7,662 $-7,662
 
Total* $6,933 $-6,933 $0 $548 $9,598 $-9,598

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/30/1996 

03/25/1997 
 

 
09/30/1996 

03/25/1997 
75  09/30/1996 

04/01/2014 


-207 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/2002 

06/30/2010 
10/15/2009 

10/15/2009 
09/30/2002 

06/30/2010 
05/01/2014 

07/01/2014 
-141 

-49 
Begin Right of Way Phase

End Right of Way Phase
12/30/2009 

12/30/2010 
10/15/2009 

10/15/2009 
12/30/2009 

12/30/2010 
05/01/2014 

07/01/2014 
-53 

-43 
Begin Construction Phase

End Construction Phase
04/30/2011 

04/30/2013 
10/15/2009 

10/15/2009 
04/30/2011 

04/30/2013 
09/01/2014 

10/31/2016 
-41 

-43 
Begin Closeout Phase

End Closeout Phase
09/30/2014 

 
 

 
09/30/2014 

 
06/30/2017 

08/31/2017 
-33 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.