Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 08C0008 - EVERGREEN RD & COTTONWOOD CREEK |
Description: Bridge No. 08C0008 - EVERGREEN RD & COTTONWOOD CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Tehama County |
City | |
Zip Code | 96022 |
Senate District |
04 |
Assembly District | 02 |
Congressional District | 02 |
Caltrans District |
02 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Tehama County | Gary Antone | (530) 385-1462 | red@tcpw.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$700 | $-700 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$6,138 | $-6,138 | $0 | ||||
Local** |
$95 | $-95 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $6,933 | $-6,933 | $0 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$828 | $-828 | $0 | $548 | $1,512 | $-1,512 | |
Right of Way |
$105 | $-105 | $0 | $0 | $424 | $-424 | |
Construction |
$6,000 | $-6,000 | $0 | $0 | $7,662 | $-7,662 | |
Total* | $6,933 | $-6,933 | $0 | $548 | $9,598 | $-9,598 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/30/1996 03/25/1997 |
|
09/30/1996 03/25/1997 |
75 | 09/30/1996 04/01/2014 |
0 -207 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/30/2002 06/30/2010 |
10/15/2009 10/15/2009 |
09/30/2002 06/30/2010 |
0 | 05/01/2014 07/01/2014 |
-141 -49 |
Begin Right of Way Phase
End Right of Way Phase |
12/30/2009 12/30/2010 |
10/15/2009 10/15/2009 |
12/30/2009 12/30/2010 |
0 | 05/01/2014 07/01/2014 |
-53 -43 |
Begin Construction Phase
End Construction Phase |
04/30/2011 04/30/2013 |
10/15/2009 10/15/2009 |
04/30/2011 04/30/2013 |
0 | 09/01/2014 10/31/2016 |
-41 -43 |
Begin Closeout Phase
End Closeout Phase |
09/30/2014 |
|
09/30/2014 |
0 | 06/30/2017 08/31/2017 |
-33 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.