Caltrans Logo

Bridge No. 08C0009 - BOWMAN ROAD & FORK COTTONWOOD

Description: Bridge No. 08C0009 - BOWMAN ROAD & FORK COTTONWOOD - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tehama County
City
Zip Code 96022
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Tehama County Gary Antone (530) 385-1462   red@tcpw.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$812 $0 $812
Non-bond Funding
State/Federal*
$7,818 $-0 $7,818
Local**
$0 $-0 $0
Private***
$0 $0 $0
 
Total**** $8,630 $-0 $8,630

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,050 $-0 $1,050 $1,089 $1,054 $-4
Right of Way
$575 $-0 $575 $352 $332 $243
Construction
$7,004 $0 $7,004 $6,787 $7,325 $-321
 
Total* $8,630 $-0 $8,630 $8,228 $8,712 $-82

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/30/1996 

03/25/1997 
09/30/1996 

03/25/1997 
09/30/1996 

03/25/1997 
100  09/30/1996 

03/25/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/25/2000 

06/30/2008 
04/25/2000 

08/30/2012 
04/25/2000 

06/30/2008 
100  04/25/2000 

08/30/2012 


-51 
Begin Right of Way Phase

End Right of Way Phase
06/10/2008 

06/30/2009 
06/10/2008 

08/30/2012 
06/10/2008 

06/30/2009 
100  06/10/2008 

12/31/2013 


-55 
Begin Construction Phase

End Construction Phase
04/30/2009 

04/30/2011 
09/01/2012 

06/30/2015 
04/30/2009 

04/30/2011 
100  09/01/2012 

06/30/2015 
-41 

-51 
Begin Closeout Phase

End Closeout Phase
04/30/2012 

07/01/2015 
07/01/2015 

04/11/2018 
04/30/2012 

07/01/2015 
100  07/01/2015 

04/12/2018 
-39 

-34 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$811,900
Current Approved:
$802,900
Actual Expenditures:
$747,885

 

Status as of December 31, 2023.