Bridge No. 10C0034 - EUREKA HILL ROAD & GARCIA RIVER

Description: Bridge No. 10C0034 - EUREKA HILL ROAD & GARCIA RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Mendocino County
City
Zip Code 95468
 
Senate District
02
Assembly District 01
Congressional District 01
 
Caltrans District
01
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Mendocino County Howard N. Dashiell (707) 463-4363   dashielh@mendocinocounty.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$338 $-90 $249
Non-bond Funding
State/Federal*
$3,054 $-238 $2,816
Local**
$57 $141 $198
Private***
$0 $0 $0
 
Total**** $3,450 $-187 $3,263

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$500 $490 $990 $960 $1,029 $-39
Right of Way
$150 $-46 $104 $104 $110 $-6
Construction
$2,800 $-631 $2,169 $2,617 $3,145 $-976
 
Total* $3,450 $-187 $3,263 $3,682 $4,283 $-1,020

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/14/2008 

06/16/2008 
 

 
04/14/2008 

06/16/2008 
100  04/14/2008 

04/05/2010 


-22 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/2008 

06/14/2010 
 

 
06/30/2008 

02/28/2020 
100  04/06/2010 

02/28/2021 
-21 

-12 
Begin Right of Way Phase

End Right of Way Phase
10/03/2010 

05/02/2011 
 

 
09/30/2014 

09/30/2014 
100  09/17/2014 

08/15/2019 


-59 
Begin Construction Phase

End Construction Phase
10/01/2011 

03/01/2013 
 

 
11/30/2020 

12/31/2024 
90  02/28/2021 

06/30/2024 
-3 

Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

12/31/2025 
07/01/2024 

06/30/2025 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.