Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 10C0034 - EUREKA HILL ROAD & GARCIA RIVER |
Description: Bridge No. 10C0034 - EUREKA HILL ROAD & GARCIA RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Mendocino County |
City | |
Zip Code | 95468 |
Senate District |
02 |
Assembly District | 01 |
Congressional District | 01 |
Caltrans District |
01 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Mendocino County | Howard N. Dashiell | (707) 463-4363 | dashielh@mendocinocounty.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$338 | $-90 | $249 | ||||
Non-bond Funding | |||||||
State/Federal* |
$3,054 | $-238 | $2,816 | ||||
Local** |
$57 | $141 | $198 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $3,450 | $-187 | $3,263 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$500 | $490 | $990 | $960 | $1,029 | $-39 | |
Right of Way |
$150 | $-46 | $104 | $104 | $110 | $-6 | |
Construction |
$2,800 | $-631 | $2,169 | $2,617 | $3,145 | $-976 | |
Total* | $3,450 | $-187 | $3,263 | $3,682 | $4,283 | $-1,020 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
04/14/2008 06/16/2008 |
|
04/14/2008 06/16/2008 |
100 | 04/14/2008 04/05/2010 |
0 -22 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/30/2008 06/14/2010 |
|
06/30/2008 02/28/2020 |
100 | 04/06/2010 02/28/2021 |
-21 -12 |
Begin Right of Way Phase
End Right of Way Phase |
10/03/2010 05/02/2011 |
|
09/30/2014 09/30/2014 |
100 | 09/17/2014 08/15/2019 |
0 -59 |
Begin Construction Phase
End Construction Phase |
10/01/2011 03/01/2013 |
|
11/30/2020 12/31/2024 |
90 | 02/28/2021 06/30/2024 |
-3 6 |
Begin Closeout Phase
End Closeout Phase |
|
|
12/31/2025 |
0 | 07/01/2024 06/30/2025 |
0 6 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.