Caltrans Logo

Bridge No. 10C0048 - MOORE AVE & WEST BRANCH RUSSIAN RIV

Description: BRIDGE NO. 10C0048 - MOORE STREET & WEST BRANCH RUSSIAN RIV - BRIDGE SEISMIC RETROFIT

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Mendocino County
City
Zip Code 95418
 
Senate District
02
Assembly District 01
Congressional District 01
 
Caltrans District
01
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Mendocino County Howard N. Dashiell (707) 463-4363   dashielh@co.mendocino.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$195 $5 $200
Non-bond Funding
State/Federal*
$1,871 $-16 $1,855
Local**
$46 $31 $77
Private***
$2,100 $26 $2,126
 
Total**** $4,211 $46 $4,257

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$2,500 $9 $2,509 $2,353 $412 $2,096
Right of Way
$111 $-57 $55 $52 $47 $8
Construction
$1,600 $94 $1,694 $1,481 $1,481 $213
 
Total* $4,211 $46 $4,257 $3,886 $1,940 $2,317

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/14/2008 

06/16/2008 
 

 
04/14/2008 

06/16/2008 
100  04/14/2008 

01/14/2009 


-7 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/2008 

06/14/2010 
10/15/2009 

10/15/2009 
06/30/2008 

06/14/2010 
100  04/06/2010 

03/04/2016 
-21 

-70 
Begin Right of Way Phase

End Right of Way Phase
10/03/2010 

05/02/2011 
10/15/2009 

10/15/2009 
10/03/2010 

05/02/2011 
100  07/01/2014 

03/04/2016 
-46 

-59 
Begin Construction Phase

End Construction Phase
10/01/2011 

09/30/2012 
10/15/2009 

10/15/2009 
10/01/2011 

09/30/2012 
100  04/19/2016 

03/31/2017 
-55 

-55 
Begin Closeout Phase

End Closeout Phase
09/30/2012 

03/30/2013 
 

 
09/30/2012 

03/30/2013 
100  03/31/2017 

12/01/2017 
-55 

-57 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$194,990
Current Approved:
$194,293
Actual Expenditures:
$169,229

 

Status as of December 31, 2023.