Caltrans Logo

Bridge No. 12C0120 - ORD FERRY RD & SACRAMENTO RIVER

Description: Bridge No. 12C0120 - ORD FERRY RD & SACRAMENTO RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Butte County
City
Zip Code 95965
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Butte County Raymond Cooper (530) 538-7681   rcooper@buttecounty.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$1,505 $-151 $1,354
Non-bond Funding
State/Federal*
$12,011 $-1,164 $10,847
Local**
$99 $0 $99
Private***
$0 $0 $0
 
Total**** $13,615 $-1,315 $12,300

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$495 $0 $495 $817 $817 $-322
Right of Way
$25 $0 $25 $60 $60 $-35
Construction
$13,095 $-1,315 $11,780 $11,402 $11,402 $378
 
Total* $13,615 $-1,315 $12,300 $12,278 $12,278 $22

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
10/16/2007 

01/31/2008 
10/15/2009 

10/15/2009 
10/16/2007 

01/31/2008 
100  10/16/2007 

12/15/2009 


-23 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/01/2008 

06/01/2010 
10/15/2009 

10/15/2009 
02/01/2008 

02/01/2011 
100  12/16/2009 

02/29/2012 
-23 

-13 
Begin Right of Way Phase

End Right of Way Phase
06/01/2008 

02/01/2010 
10/15/2009 

10/15/2009 
06/01/2008 

02/01/2011 
100  11/01/2010 

02/29/2012 
-29 

-13 
Begin Construction Phase

End Construction Phase
03/01/2011 

06/30/2014 
10/15/2009 

10/15/2009 
03/01/2012 

06/30/2015 
100  03/01/2012 

10/30/2013 


20 
Begin Closeout Phase

End Closeout Phase
12/31/2014 

 
 

05/08/2015 
06/30/2015 

12/31/2015 
100  07/09/2014 

03/15/2019 
12 

-39 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$1,505,000
Current Approved:
$1,351,166
Actual Expenditures:
$1,333,439

 

Status as of December 31, 2023.