Bridge No. 17C0045 - HIRSCHDALE RD & TRUCKEE RIVER

Description: Bridge No. 17C0045 - HIRSCHDALE RD & TRUCKEE RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Nevada County
City
Zip Code 96161
 
Senate District
01
Assembly District 03
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Nevada County David Garcia (530) 265-7038   david.garcia@co.nevada.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$315 $-315 $0
Non-bond Funding
State/Federal*
$4,704 $-4,704 $0
Local**
$381 $-381 $0
Private***
$0 $0 $0
 
Total**** $5,400 $-5,400 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$900 $-900 $0 $0 $0 $0
Right of Way
$100 $-100 $0 $0 $0 $0
Construction
$4,400 $-4,400 $0 $0 $0 $0
 
Total* $5,400 $-5,400 $0 $0 $0 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

08/30/2002 
 

 
 

08/30/2002 
100   

08/30/2002 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/2002 

12/30/2009 
10/15/2009 

10/15/2009 
09/30/2002 

05/30/2011 
75  09/30/2002 

06/30/2014 


-38 
Begin Right of Way Phase

End Right of Way Phase
06/30/2009 

11/30/2009 
10/15/2009 

10/15/2009 
06/30/2009 

06/30/2011 
50  06/30/2009 

06/30/2014 


-37 
Begin Construction Phase

End Construction Phase
06/30/2010 

05/30/2012 
10/15/2009 

10/15/2009 
06/01/2012 

10/30/2013 
07/01/2015 

06/30/2016 
-37 

-32 
Begin Closeout Phase

End Closeout Phase
11/30/2012 

 
 

 
11/30/2012 

 
07/01/2016 

06/30/2017 
-44 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.