Bridge No. 20C0017 - WATMAUGH ROAD & SONOMA CREEK |
Description: Bridge No. 20C0017 - WATMAUGH ROAD & SONOMA CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Sonoma County |
City | |
Zip Code | 95476 |
Senate District |
02 |
Assembly District | 06 |
Congressional District | 06 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Sonoma County | Johannes Hoevertsz | (707) 565-3585 | Johannes.Hoevertsz@sonoma-county.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$585 | $-506 | $79 | ||||
Non-bond Funding | |||||||
State/Federal* |
$5,563 | $2,107 | $7,670 | ||||
Local** |
$52 | $849 | $901 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $6,200 | $2,450 | $8,650 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$1,052 | $535 | $1,587 | $1,315 | $1,639 | $-53 | |
Right of Way |
$200 | $52 | $252 | $45 | $250 | $2 | |
Construction |
$4,949 | $1,863 | $6,812 | $0 | $5,000 | $1,812 | |
Total* | $6,200 | $2,450 | $8,650 | $1,359 | $6,889 | $1,761 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/30/1997 06/01/2008 |
|
09/30/1997 06/01/2008 |
100 | 09/30/1997 06/01/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2008 01/01/2009 |
|
07/07/2009 02/28/2024 |
100 | 07/01/2009 12/29/2023 |
0 2 |
Begin Right of Way Phase
End Right of Way Phase |
01/01/2009 06/01/2009 |
|
01/30/2021 12/31/2023 |
50 | 10/01/2020 06/30/2024 |
4 -6 |
Begin Construction Phase
End Construction Phase |
05/01/2010 05/01/2011 |
|
03/31/2024 03/31/2027 |
0 | 09/01/2024 12/31/2026 |
-5 3 |
Begin Closeout Phase
End Closeout Phase |
|
|
06/30/2028 |
0 | 01/01/2027 06/30/2027 |
0 12 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.