Bridge No. 20C0017 - WATMAUGH ROAD & SONOMA CREEK

Description: Bridge No. 20C0017 - WATMAUGH ROAD & SONOMA CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Sonoma County
City
Zip Code 95476
 
Senate District
02
Assembly District 06
Congressional District 06
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Sonoma County Johannes Hoevertsz (707) 565-3585   Johannes.Hoevertsz@sonoma-county.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$585 $-506 $79
Non-bond Funding
State/Federal*
$5,563 $2,107 $7,670
Local**
$52 $849 $901
Private***
$0 $0 $0
 
Total**** $6,200 $2,450 $8,650

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,052 $535 $1,587 $1,315 $1,639 $-53
Right of Way
$200 $52 $252 $45 $250 $2
Construction
$4,949 $1,863 $6,812 $0 $5,000 $1,812
 
Total* $6,200 $2,450 $8,650 $1,359 $6,889 $1,761

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/30/1997 

06/01/2008 
 

 
09/30/1997 

06/01/2008 
100  09/30/1997 

06/01/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2008 

01/01/2009 
 

 
07/07/2009 

02/28/2024 
100  07/01/2009 

12/29/2023 


Begin Right of Way Phase

End Right of Way Phase
01/01/2009 

06/01/2009 
 

 
01/30/2021 

12/31/2023 
50  10/01/2020 

06/30/2024 


-6 
Begin Construction Phase

End Construction Phase
05/01/2010 

05/01/2011 
 

 
03/31/2024 

03/31/2027 
09/01/2024 

12/31/2026 
-5 

Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

06/30/2028 
01/01/2027 

06/30/2027 


12 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.