Bridge No. 20C0065 - HEALDSBURG AVE & RUSSIAN RIVER |
Description: Bridge No. 20C0065 - HEALDSBURG AVE & RUSSIAN RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sonoma County |
City | Healdsburg |
Zip Code | 95448 |
Senate District |
02 |
Assembly District | 01 |
Congressional District | 01 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Healdsburg | Clay Thistle | (707) 431-3391 | cthistle@ci.healdsburg.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$250 | $0 | $250 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,505 | $12,746 | $15,251 | ||||
Local** |
$75 | $1,651 | $1,726 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $2,830 | $14,397 | $17,227 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$650 | $2,772 | $3,422 | $3,545 | $3,545 | $-123 | |
Right of Way |
$50 | $0 | $50 | $6 | $6 | $44 | |
Construction |
$2,130 | $11,625 | $13,755 | $15,082 | $15,082 | $-1,327 | |
Total* | $2,830 | $14,397 | $17,227 | $18,633 | $18,633 | $-1,406 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
06/30/1998 06/30/1999 |
|
07/08/2009 02/28/2011 |
100 | 06/30/1998 06/30/1999 |
134 142 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/30/2010 06/30/2011 |
10/15/2009 10/15/2009 |
07/08/2009 07/08/2009 |
100 | 02/01/2013 01/31/2014 |
-43 -56 |
Begin Right of Way Phase
End Right of Way Phase |
08/30/2010 06/30/2011 |
10/15/2009 10/15/2009 |
03/04/2014 04/08/2014 |
100 | 02/01/2012 01/31/2014 |
25 2 |
Begin Construction Phase
End Construction Phase |
01/30/2012 06/30/2014 |
10/15/2009 10/15/2009 |
04/08/2014 05/06/2016 |
100 | 08/04/2014 05/06/2016 |
-4 0 |
Begin Closeout Phase
End Closeout Phase |
01/30/2015 08/20/2018 |
|
01/30/2015 08/20/2018 |
100 | 05/09/2016 07/08/2019 |
-15 -11 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$250,046 |
Current Approved: |
$244,311 |
Actual Expenditures: |
$244,311 |
Status as of December 31, 2023.