Caltrans Logo

Bridge No. 20C0065 - HEALDSBURG AVE & RUSSIAN RIVER

Description: Bridge No. 20C0065 - HEALDSBURG AVE & RUSSIAN RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sonoma County
City Healdsburg
Zip Code 95448
 
Senate District
02
Assembly District 01
Congressional District 01
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Healdsburg Clay Thistle (707) 431-3391   cthistle@ci.healdsburg.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$250 $0 $250
Non-bond Funding
State/Federal*
$2,505 $12,746 $15,251
Local**
$75 $1,651 $1,726
Private***
$0 $0 $0
 
Total**** $2,830 $14,397 $17,227

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$650 $2,772 $3,422 $3,545 $3,545 $-123
Right of Way
$50 $0 $50 $6 $6 $44
Construction
$2,130 $11,625 $13,755 $15,082 $15,082 $-1,327
 
Total* $2,830 $14,397 $17,227 $18,633 $18,633 $-1,406

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
06/30/1998 

06/30/1999 
 

 
07/08/2009 

02/28/2011 
100  06/30/1998 

06/30/1999 
134 

142 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/30/2010 

06/30/2011 
10/15/2009 

10/15/2009 
07/08/2009 

07/08/2009 
100  02/01/2013 

01/31/2014 
-43 

-56 
Begin Right of Way Phase

End Right of Way Phase
08/30/2010 

06/30/2011 
10/15/2009 

10/15/2009 
03/04/2014 

04/08/2014 
100  02/01/2012 

01/31/2014 
25 

Begin Construction Phase

End Construction Phase
01/30/2012 

06/30/2014 
10/15/2009 

10/15/2009 
04/08/2014 

05/06/2016 
100  08/04/2014 

05/06/2016 
-4 

Begin Closeout Phase

End Closeout Phase
01/30/2015 

08/20/2018 
 

 
01/30/2015 

08/20/2018 
100  05/09/2016 

07/08/2019 
-15 

-11 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$250,046
Current Approved:
$244,311
Actual Expenditures:
$244,311

 

Status as of December 31, 2023.