Bridge No. 20C0139 - WOHLER RD & MARK WEST CREEK

Description: Bridge No. 20C0139 - WOHLER RD & MARK WEST CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sonoma County
City
Zip Code 95436
 
Senate District
02
Assembly District 01
Congressional District 06
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Sonoma County Susan Klassen (707) 565-2231   Susan.Klassen@sonoma-county.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$585 $-585 $0
Non-bond Funding
State/Federal*
$3,894 $-3,894 $0
Local**
$37 $-37 $0
Private***
$0 $0 $0
 
Total**** $4,516 $-4,516 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $0 $0 $0 $1,052 $-1,052
Right of Way
$200 $-200 $0 $0 $177 $-177
Construction
$4,316 $-4,316 $0 $0 $4,386 $-4,386
 
Total* $4,516 $-4,516 $0 $0 $5,615 $-5,615

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/30/1997 

12/30/1997 
 

 
09/30/1997 

12/30/1997 
100  09/30/1997 

12/30/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/30/1997 

12/01/2008 
 

10/15/2009 
12/30/1997 

12/01/2010 
25  12/30/1997 

06/30/2015 


-56 
Begin Right of Way Phase

End Right of Way Phase
12/01/2007 

12/01/2008 
 

10/15/2009 
12/01/2007 

06/01/2011 
12/01/2011 

06/30/2015 
-49 

-50 
Begin Construction Phase

End Construction Phase
05/01/2009 

05/01/2010 
10/15/2009 

10/15/2009 
05/01/2012 

11/01/2012 
07/01/2015 

11/01/2015 
-39 

-36 
Begin Closeout Phase

End Closeout Phase
10/01/2010 

 
 

 
10/01/2010 

 
11/01/2015 

11/01/2016 
-62 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.