Bridge No. 20C0141 - ANNAPOLIS RD & GUALALA RIV (CLARK XING)

Description: Bridge No. 20C0141 - ANNAPOLIS RD & GUALALA RIV (CLARK XING) - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sonoma County
City
Zip Code 95412
 
Senate District
02
Assembly District 01
Congressional District 06
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Sonoma County Susan Klassen (707) 565-2231   susan.klassen@sonoma-county.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$166 $35 $201
Non-bond Funding
State/Federal*
$1,615 $201 $1,816
Local**
$15 $0 $15
Private***
$0 $0 $0
 
Total**** $1,796 $236 $2,032

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$309 $-84 $225 $725 $725 $-500
Right of Way
$31 $14 $45 $47 $47 $-2
Construction
$1,455 $307 $1,762 $1,345 $1,345 $417
 
Total* $1,796 $236 $2,032 $2,117 $2,117 $-85

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/30/1997 

12/30/1997 
 

 
09/30/1997 

12/30/1997 
100  09/30/1997 

12/30/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/30/1997 

02/01/2008 
 

 
12/30/1997 

02/01/2008 
100  12/30/1997 

02/01/2008 


Begin Right of Way Phase

End Right of Way Phase
11/18/2005 

12/01/2007 
 

 
11/18/2005 

12/01/2007 
100  11/18/2005 

12/01/2007 


Begin Construction Phase

End Construction Phase
05/01/2008 

05/01/2009 
10/15/2009 

10/15/2009 
05/01/2010 

11/01/2010 
100  09/01/2010 

11/01/2011 
-4 

-12 
Begin Closeout Phase

End Closeout Phase
09/01/2009 

 
 

 
09/01/2009 

 
50  11/01/2012 

12/14/2012 
-39 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$165,510
Current Approved:
$200,725
Actual Expenditures:
$154,327

 

Status as of December 31, 2023.