Bridge No. 20C0242 - CHALK HILL RD & MAACAMA CREEK

Description: Bridge No. 20C0242 - CHALK HILL RD & MAACAMA CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sonoma County
City
Zip Code 95448
 
Senate District
02
Assembly District 01
Congressional District 01
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Sonoma County Phillip Demery (707) 565-2231   pdemery@sonoma-county.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$586 $-586 $0
Non-bond Funding
State/Federal*
$5,467 $-5,467 $0
Local**
$52 $-52 $0
Private***
$0 $0 $0
 
Total**** $6,105 $-6,105 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$952 $-952 $0 $0 $1,074 $-1,074
Right of Way
$100 $-100 $0 $0 $89 $-89
Construction
$5,053 $-5,053 $0 $0 $4,480 $-4,480
 
Total* $6,105 $-6,105 $0 $0 $5,643 $-5,643

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/30/1997 

06/01/2008 
 

 
09/30/1997 

06/01/2008 
09/30/1997 

06/01/2020 


-146 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2008 

06/01/2009 
 

10/15/2009 
06/01/2008 

01/01/2015 
06/01/2020 

06/01/2022 
-146 

-90 
Begin Right of Way Phase

End Right of Way Phase
06/01/2009 

01/01/2010 
 

10/15/2009 
06/01/2009 

01/01/2015 
06/01/2022 

01/01/2023 
-158 

-97 
Begin Construction Phase

End Construction Phase
05/01/2010 

05/01/2011 
10/15/2009 

10/15/2009 
05/01/2016 

11/01/2016 
05/01/2023 

11/01/2023 
-85 

-85 
Begin Closeout Phase

End Closeout Phase
10/01/2011 

 
 

 
10/01/2011 

 
11/01/2024 

 
-159 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.