Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 20C0248 - LAMBERT BRIDGE RD & DRY CREEK |
Description: Bridge No. 20C0248 - LAMBERT BRIDGE RD & DRY CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sonoma County |
City | |
Zip Code | 95448 |
Senate District |
02 |
Assembly District | 01 |
Congressional District | 06 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Sonoma County | Susan Klassen | (707) 565-2231 | Susan.Klassen@sonoma-county.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$583 | $-583 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$5,563 | $-5,563 | $0 | ||||
Local** |
$52 | $-52 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $6,198 | $-6,198 | $0 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$1,069 | $-1,069 | $0 | $0 | $1,069 | $-1,069 | |
Right of Way |
$100 | $-100 | $0 | $0 | $89 | $-89 | |
Construction |
$5,029 | $-5,029 | $0 | $0 | $4,459 | $-4,459 | |
Total* | $6,198 | $-6,198 | $0 | $0 | $5,617 | $-5,617 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/30/1997 06/01/2008 |
|
09/30/1997 06/01/2008 |
100 | 09/30/1997 09/30/2011 |
0 -41 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2008 06/01/2009 |
10/15/2009 |
06/01/2008 09/30/2015 |
0 | 09/30/2011 09/30/2015 |
-41 0 |
Begin Right of Way Phase
End Right of Way Phase |
06/01/2009 01/01/2010 |
10/15/2009 |
06/01/2009 09/30/2015 |
0 | 09/30/2014 09/30/2015 |
-65 0 |
Begin Construction Phase
End Construction Phase |
05/01/2010 05/01/2011 |
10/15/2009 10/15/2009 |
05/01/2016 10/01/2016 |
0 | 05/01/2016 10/01/2016 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
10/01/2011 |
10/15/2009 |
10/01/2017 |
0 | 10/01/2017 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.