Bridge No. 20C0262 - BOYES BLVD & SONOMA CREEK

Description: Bridge No. 20C0262 - BOYES BLVD & SONOMA CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sonoma County
City
Zip Code 95476
 
Senate District
02
Assembly District 06
Congressional District 06
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Sonoma County Johannes Hoevertsz (707) 565-3585   Johannes.Hoevertsz@sonoma-county.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$638 $-564 $74
Non-bond Funding
State/Federal*
$6,053 $1,634 $7,687
Local**
$56 $1,006 $1,062
Private***
$0 $0 $0
 
Total**** $6,747 $2,075 $8,822

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,087 $620 $1,707 $2,268 $2,268 $-562
Right of Way
$504 $302 $806 $816 $816 $-10
Construction
$5,156 $1,153 $6,309 $7,109 $7,109 $-799
 
Total* $6,747 $2,075 $8,822 $10,193 $10,193 $-1,371

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/30/1997 

09/30/1999 
 

 
09/30/1997 

09/30/1999 
100  09/30/1997 

04/29/1999 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/15/1999 

06/01/2008 
10/15/2009 

10/15/2009 
07/28/1999 

06/01/2013 
100  07/28/1999 

05/15/2019 


-72 
Begin Right of Way Phase

End Right of Way Phase
06/01/2008 

12/01/2008 
10/15/2009 

10/15/2009 
06/01/2008 

06/01/2013 
100  05/21/2013 

12/11/2018 
-60 

-67 
Begin Construction Phase

End Construction Phase
05/01/2009 

05/01/2010 
10/15/2009 

10/15/2009 
06/01/2015 

07/01/2016 
100  04/19/2019 

03/04/2022 
-47 

-69 
Begin Closeout Phase

End Closeout Phase
10/01/2010 

 
 

 
10/01/2016 

 
50  03/04/2022 

12/07/2023 
-66 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$638,244
Current Approved:
$73,809
Actual Expenditures:
$73,809

 

Status as of December 31, 2023.