Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 20C0262 - BOYES BLVD & SONOMA CREEK |
Description: Bridge No. 20C0262 - BOYES BLVD & SONOMA CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sonoma County |
City | |
Zip Code | 95476 |
Senate District |
02 |
Assembly District | 06 |
Congressional District | 06 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Sonoma County | Johannes Hoevertsz | (707) 565-3585 | Johannes.Hoevertsz@sonoma-county.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$638 | $-564 | $74 | ||||
Non-bond Funding | |||||||
State/Federal* |
$6,053 | $1,634 | $7,687 | ||||
Local** |
$56 | $1,006 | $1,062 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $6,747 | $2,075 | $8,822 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$1,087 | $620 | $1,707 | $2,268 | $2,268 | $-562 | |
Right of Way |
$504 | $302 | $806 | $816 | $816 | $-10 | |
Construction |
$5,156 | $1,153 | $6,309 | $7,109 | $7,109 | $-799 | |
Total* | $6,747 | $2,075 | $8,822 | $10,193 | $10,193 | $-1,371 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/30/1997 09/30/1999 |
|
09/30/1997 09/30/1999 |
100 | 09/30/1997 04/29/1999 |
0 5 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/15/1999 06/01/2008 |
10/15/2009 10/15/2009 |
07/28/1999 06/01/2013 |
100 | 07/28/1999 05/15/2019 |
0 -72 |
Begin Right of Way Phase
End Right of Way Phase |
06/01/2008 12/01/2008 |
10/15/2009 10/15/2009 |
06/01/2008 06/01/2013 |
100 | 05/21/2013 12/11/2018 |
-60 -67 |
Begin Construction Phase
End Construction Phase |
05/01/2009 05/01/2010 |
10/15/2009 10/15/2009 |
06/01/2015 07/01/2016 |
100 | 04/19/2019 03/04/2022 |
-47 -69 |
Begin Closeout Phase
End Closeout Phase |
10/01/2010 |
|
10/01/2016 |
50 | 03/04/2022 12/07/2023 |
-66 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$638,244 |
Current Approved: |
$73,809 |
Actual Expenditures: |
$73,809 |
Status as of December 31, 2023.