Bridge No. 20C0407 - WEST DRY CREEK RD & PENA CREEK

Description: Bridge No. 20C0407 - WEST DRY CREEK RD & PENA CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sonoma County
City
Zip Code 95448
 
Senate District
02
Assembly District 01
Congressional District 06
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Sonoma County Susan Klassen (707) 565-2231   Susan.Klassen@sonoma-county.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$583 $-583 $0
Non-bond Funding
State/Federal*
$5,565 $-5,565 $0
Local**
$52 $-52 $0
Private***
$0 $0 $0
 
Total**** $6,200 $-6,200 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,069 $-1,069 $0 $0 $1,069 $-1,069
Right of Way
$100 $-100 $0 $0 $89 $-89
Construction
$5,031 $-5,031 $0 $0 $4,459 $-4,459
 
Total* $6,200 $-6,200 $0 $0 $5,617 $-5,617

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/30/1997 

06/01/2008 
 

 
09/30/1997 

06/01/2008 
100  09/30/1997 

06/01/2009 


-12 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2008 

01/01/2009 
10/15/2009 

10/15/2009 
06/01/2008 

12/01/2012 
12/01/2009 

12/01/2016 
-18 

-49 
Begin Right of Way Phase

End Right of Way Phase
01/01/2009 

06/01/2009 
10/15/2009 

10/15/2009 
01/01/2009 

12/01/2012 
12/01/2015 

12/01/2016 
-84 

-49 
Begin Construction Phase

End Construction Phase
05/01/2010 

05/01/2011 
10/15/2009 

10/15/2009 
05/01/2015 

10/01/2015 
05/01/2017 

10/01/2017 
-24 

-24 
Begin Closeout Phase

End Closeout Phase
10/01/2011 

 
10/15/2009 

 
10/01/2016 

 
10/01/2017 

10/01/2017 
-12 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.