Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 22C0074 - CO RD 57 & CACHE CREEK |
Description: Bridge No. 22C0074 - CO RD 57 & CACHE CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Yolo County |
City | |
Zip Code | 95937 |
Senate District |
05 |
Assembly District | 02 |
Congressional District | 02 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Yolo County | Jim Campbell | (530) 666-8847 | jcampbell@yolocounty.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$231 | $-5 | $226 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,253 | $397 | $2,650 | ||||
Local** |
$107 | $63 | $171 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $2,592 | $454 | $3,046 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$536 | $43 | $580 | $580 | $580 | $0 | |
Right of Way |
$40 | $-18 | $22 | $22 | $22 | $0 | |
Construction |
$2,015 | $429 | $2,444 | $2,444 | $2,444 | $0 | |
Total* | $2,592 | $454 | $3,046 | $3,046 | $3,046 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
05/18/2001 11/01/2001 |
|
05/18/2001 11/01/2001 |
100 | 05/18/2001 08/01/2001 |
0 3 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/01/2001 02/01/2010 |
|
10/01/2001 09/09/2009 |
100 | 10/01/2001 09/09/2009 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
05/31/2008 12/30/2008 |
10/15/2009 |
07/28/2008 10/15/2009 |
100 | 08/29/2007 12/30/2008 |
11 10 |
Begin Construction Phase
End Construction Phase |
05/01/2010 06/30/2011 |
10/15/2009 10/15/2009 |
05/01/2010 06/30/2012 |
100 | 06/01/2010 03/04/2011 |
-1 16 |
Begin Closeout Phase
End Closeout Phase |
12/31/2011 01/31/2013 |
|
12/31/2011 01/31/2013 |
100 | 12/31/2012 06/14/2013 |
-12 -4 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$231,120 |
Current Approved: |
$225,697 |
Actual Expenditures: |
$225,697 |
Status as of December 31, 2023.