Bridge No. 22C0074 - CO RD 57 & CACHE CREEK

Description: Bridge No. 22C0074 - CO RD 57 & CACHE CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Yolo County
City
Zip Code 95937
 
Senate District
05
Assembly District 02
Congressional District 02
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Yolo County Jim Campbell (530) 666-8847   jcampbell@yolocounty.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$231 $-5 $226
Non-bond Funding
State/Federal*
$2,253 $397 $2,650
Local**
$107 $63 $171
Private***
$0 $0 $0
 
Total**** $2,592 $454 $3,046

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$536 $43 $580 $580 $580 $0
Right of Way
$40 $-18 $22 $22 $22 $0
Construction
$2,015 $429 $2,444 $2,444 $2,444 $0
 
Total* $2,592 $454 $3,046 $3,046 $3,046 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
05/18/2001 

11/01/2001 
 

 
05/18/2001 

11/01/2001 
100  05/18/2001 

08/01/2001 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2001 

02/01/2010 
 

 
10/01/2001 

09/09/2009 
100  10/01/2001 

09/09/2009 


Begin Right of Way Phase

End Right of Way Phase
05/31/2008 

12/30/2008 
 

10/15/2009 
07/28/2008 

10/15/2009 
100  08/29/2007 

12/30/2008 
11 

10 
Begin Construction Phase

End Construction Phase
05/01/2010 

06/30/2011 
10/15/2009 

10/15/2009 
05/01/2010 

06/30/2012 
100  06/01/2010 

03/04/2011 
-1 

16 
Begin Closeout Phase

End Closeout Phase
12/31/2011 

01/31/2013 
 

 
12/31/2011 

01/31/2013 
100  12/31/2012 

06/14/2013 
-12 

-4 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$231,120
Current Approved:
$225,697
Actual Expenditures:
$225,697

 

Status as of December 31, 2023.