Bridge No. 23C0152 - SACRAMENTO ST & US NAVY RR |
Description: Bridge No. 23C0152 - SACRAMENTO ST & US NAVY RR - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Solano County |
City | Vallejo |
Zip Code | 94590 |
Senate District |
02 |
Assembly District | 07 |
Congressional District | 07 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Vallejo | Sam Kumar | (707) 648-4432 | sam.kumar@cityofvallejo.net |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$12 | $206 | $219 | ||||
Non-bond Funding | |||||||
State/Federal* |
$9,561 | $1,289 | $10,850 | ||||
Local** |
$0 | $1,161 | $1,161 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $9,574 | $2,656 | $12,230 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $1,458 | $1,458 | $2,312 | $0 | $1,458 | |
Right of Way |
$0 | $449 | $449 | $509 | $0 | $449 | |
Construction |
$9,574 | $749 | $10,323 | $11,025 | $0 | $10,323 | |
Total* | $9,574 | $2,656 | $12,230 | $13,846 | $0 | $12,230 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
10/01/2007 04/01/2009 |
|
10/01/2007 04/01/2009 |
100 | 12/15/2011 06/30/2013 |
-51 -52 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2009 10/01/2010 |
|
05/04/2015 09/30/2019 |
100 | 06/15/2015 01/27/2020 |
-1 -4 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
05/01/2017 08/02/2019 |
100 | 04/17/2017 08/02/2019 |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2010 10/01/2013 |
|
04/01/2020 06/30/2022 |
100 | 03/19/2020 09/30/2022 |
0 -3 |
Begin Closeout Phase
End Closeout Phase |
|
|
12/30/2022 |
75 | 10/03/2022 03/14/2023 |
0 -2 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$12,387 |
Current Approved: |
$218,504 |
Actual Expenditures: |
$193,442 |
Status as of December 31, 2023.