Bridge No. 27C0144 - CREEK ROAD & SAN ANSELMO CREEK

Description: Bridge No. 27C0144 - CREEK ROAD & SAN ANSELMO CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Marin County
City Fairfax
Zip Code 94930
 
Senate District
03
Assembly District 06
Congressional District 06
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Fairfax Nader Tamannaie 916-448-1980   ntamannaie@califstructure.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$22 $0 $22
Non-bond Funding
State/Federal*
$173 $0 $173
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $195 $0 $195

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $0 $0 $628 $796 $-796
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$195 $0 $195 $0 $1,516 $-1,321
 
Total* $195 $0 $195 $628 $2,312 $-2,117

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
01/01/2008 

09/01/2008 
 

 
01/01/2008 

09/01/2008 
100  10/02/2013 

05/01/2014 
-70 

-69 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2008 

07/01/2009 
10/15/2009 

10/15/2009 
12/01/2008 

03/01/2010 
80  08/01/2014 

10/31/2017 
-69 

-93 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
04/01/2010 

09/29/2011 
03/01/2016 

12/20/2017 
-72 

-76 
Begin Construction Phase

End Construction Phase
09/30/2011 

 
10/15/2009 

10/15/2009 
09/30/2011 

12/01/2011 
04/15/2018 

03/30/2019 
-80 

-89 
Begin Closeout Phase

End Closeout Phase
12/30/2011 

 
 

 
12/30/2011 

 
03/31/2019 

04/30/2019 
-88 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.