Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 27C0150 - ALEXANDER AVE & ABANDONED NWP RR ROW |
Description: Bridge No. 27C0150 - ALEXANDER AVE & ABANDONED NWP RR ROW - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Marin County |
City | Larkspur |
Zip Code | 94939 |
Senate District |
03 |
Assembly District | 06 |
Congressional District | 06 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Larkspur | JOHN MOE | 415-927-5017 | JMOE@CITYOFLARKSPUR.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$352 | $-352 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$3,560 | $-3,560 | $0 | ||||
Local** |
$201 | $-201 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $4,114 | $-4,114 | $0 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$1,041 | $-1,041 | $0 | $1,052 | $1,052 | $-1,052 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$3,072 | $-3,072 | $0 | $0 | $1,549 | $-1,549 | |
Total* | $4,114 | $-4,114 | $0 | $1,052 | $2,601 | $-2,601 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
11/15/2007 03/15/2008 |
|
11/15/2007 03/15/2008 |
100 | 11/15/2007 12/31/2009 |
0 -22 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2008 02/06/2009 |
10/15/2009 10/15/2009 |
04/01/2008 03/31/2011 |
100 | 02/23/2009 09/30/2012 |
-11 -18 |
Begin Right of Way Phase
End Right of Way Phase |
10/01/2008 06/30/2009 |
10/15/2009 10/15/2009 |
10/01/2008 09/30/2010 |
100 | 10/01/2009 09/30/2012 |
-12 -24 |
Begin Construction Phase
End Construction Phase |
09/30/2009 12/01/2010 |
10/15/2009 10/15/2009 |
08/01/2011 09/30/2012 |
0 | 02/01/2013 12/31/2013 |
-18 -15 |
Begin Closeout Phase
End Closeout Phase |
06/30/2011 |
|
06/30/2011 |
0 | 12/31/2013 |
-30 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.