Bridge No. 27C0150 - ALEXANDER AVE & ABANDONED NWP RR ROW

Description: Bridge No. 27C0150 - ALEXANDER AVE & ABANDONED NWP RR ROW - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Marin County
City Larkspur
Zip Code 94939
 
Senate District
03
Assembly District 06
Congressional District 06
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Larkspur JOHN MOE 415-927-5017   JMOE@CITYOFLARKSPUR.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$352 $-352 $0
Non-bond Funding
State/Federal*
$3,560 $-3,560 $0
Local**
$201 $-201 $0
Private***
$0 $0 $0
 
Total**** $4,114 $-4,114 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,041 $-1,041 $0 $1,052 $1,052 $-1,052
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,072 $-3,072 $0 $0 $1,549 $-1,549
 
Total* $4,114 $-4,114 $0 $1,052 $2,601 $-2,601

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
11/15/2007 

03/15/2008 
 

 
11/15/2007 

03/15/2008 
100  11/15/2007 

12/31/2009 


-22 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2008 

02/06/2009 
10/15/2009 

10/15/2009 
04/01/2008 

03/31/2011 
100  02/23/2009 

09/30/2012 
-11 

-18 
Begin Right of Way Phase

End Right of Way Phase
10/01/2008 

06/30/2009 
10/15/2009 

10/15/2009 
10/01/2008 

09/30/2010 
100  10/01/2009 

09/30/2012 
-12 

-24 
Begin Construction Phase

End Construction Phase
09/30/2009 

12/01/2010 
10/15/2009 

10/15/2009 
08/01/2011 

09/30/2012 
02/01/2013 

12/31/2013 
-18 

-15 
Begin Closeout Phase

End Closeout Phase
06/30/2011 

 
 

 
06/30/2011 

 
12/31/2013 

 
-30 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.