Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 28C0054 - WILBUR AVE & BNSF RY & AMTRAK, UP RR |
Description: Bridge No. 28C0054 - WILBUR AVE & BNSF RY & AMTRAK, UP RR - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Contra Costa County |
City | Antioch |
Zip Code | 94531 |
Senate District |
07 |
Assembly District | 11 |
Congressional District | 10 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Antioch | Tracy Shearer | (925) 779-6130 | tshearer@ci.antioch.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$103 | $-0 | $103 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,709 | $11,667 | $13,377 | ||||
Local** |
$118 | $1,622 | $1,740 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,931 | $13,289 | $15,220 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$751 | $394 | $1,145 | $0 | $0 | $1,145 | |
Right of Way |
$280 | $0 | $280 | $0 | $0 | $280 | |
Construction |
$900 | $12,895 | $13,795 | $13,138 | $13,138 | $657 | |
Total* | $1,931 | $13,289 | $15,220 | $13,138 | $13,138 | $2,082 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
|
|
12/03/1998 |
100 | 12/03/1998 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/30/2008 |
10/15/2009 |
01/26/2010 |
100 | 02/29/2012 |
0 -25 |
Begin Right of Way Phase
End Right of Way Phase |
01/30/2008 02/28/2009 |
10/15/2009 10/15/2009 |
01/30/2008 06/07/2010 |
100 | 01/30/2008 02/15/2012 |
0 -21 |
Begin Construction Phase
End Construction Phase |
09/30/2009 09/30/2011 |
10/15/2009 |
03/31/2013 03/31/2016 |
100 | 01/07/2013 07/09/2014 |
3 21 |
Begin Closeout Phase
End Closeout Phase |
11/30/2012 |
|
04/02/2016 |
100 | 11/03/2014 02/01/2015 |
17 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$103,230 |
Current Approved: |
$103,000 |
Actual Expenditures: |
$113,000 |
Status as of December 31, 2023.