Bridge No. 28C0054 - WILBUR AVE & BNSF RY & AMTRAK, UP RR

Description: Bridge No. 28C0054 - WILBUR AVE & BNSF RY & AMTRAK, UP RR - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa County
City Antioch
Zip Code 94531
 
Senate District
07
Assembly District 11
Congressional District 10
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Antioch Tracy Shearer (925) 779-6130   tshearer@ci.antioch.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$103 $-0 $103
Non-bond Funding
State/Federal*
$1,709 $11,667 $13,377
Local**
$118 $1,622 $1,740
Private***
$0 $0 $0
 
Total**** $1,931 $13,289 $15,220

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$751 $394 $1,145 $0 $0 $1,145
Right of Way
$280 $0 $280 $0 $0 $280
Construction
$900 $12,895 $13,795 $13,138 $13,138 $657
 
Total* $1,931 $13,289 $15,220 $13,138 $13,138 $2,082

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

 
 

 
 

12/03/1998 
100   

12/03/1998 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

11/30/2008 
 

10/15/2009 
 

01/26/2010 
100   

02/29/2012 


-25 
Begin Right of Way Phase

End Right of Way Phase
01/30/2008 

02/28/2009 
10/15/2009 

10/15/2009 
01/30/2008 

06/07/2010 
100  01/30/2008 

02/15/2012 


-21 
Begin Construction Phase

End Construction Phase
09/30/2009 

09/30/2011 
10/15/2009 

 
03/31/2013 

03/31/2016 
100  01/07/2013 

07/09/2014 


21 
Begin Closeout Phase

End Closeout Phase
11/30/2012 

 
 

 
04/02/2016 

 
100  11/03/2014 

02/01/2015 
17 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$103,230
Current Approved:
$103,000
Actual Expenditures:
$113,000

 

Status as of December 31, 2023.