Bridge No. 28C0165 - NORTH PARKSIDE DR & WILLOW PASS ROAD

Description: Bridge No. 28C0165 - NORTH PARKSIDE DR & WILLOW PASS ROAD - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa County
City Pittsburg
Zip Code 94565
 
Senate District
07
Assembly District 11
Congressional District 07
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Pittsburg SM Saklaen (925) 252-6943   smsaklaen@ci.pittsburg.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$57 $-11 $46
Non-bond Funding
State/Federal*
$564 $88 $653
Local**
$16 $23 $38
Private***
$0 $0 $0
 
Total**** $637 $100 $737

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$138 $92 $229 $237 $0 $229
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$500 $8 $508 $547 $0 $508
 
Total* $637 $100 $737 $783 $0 $737

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
02/28/2008 

04/30/2008 
 

 
02/28/2008 

11/30/2009 
100  07/14/2008 

07/20/2012 
-4 

-32 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/2008 

09/30/2008 
 

10/15/2009 
06/30/2008 

03/28/2010 
100  04/21/2011 

12/21/2017 
-34 

-94 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

10/15/2009 
 

02/15/2010 
100  03/05/2015 

03/30/2015 


-62 
Begin Construction Phase

End Construction Phase
03/30/2009 

07/30/2009 
10/15/2009 

10/15/2009 
04/28/2010 

07/30/2010 
100  12/22/2017 

05/30/2019 
-93 

-108 
Begin Closeout Phase

End Closeout Phase
02/28/2010 

 
 

 
07/30/2010 

 
100  08/15/2019 

09/23/2019 
-110 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$57,400
Current Approved:
$57,400
Actual Expenditures:
$57,400

 

Status as of December 31, 2023.