Bridge No. 28C0330 - MINER RD & SAN PABLO CREEK

Description: Bridge No. 28C0330 - MINER RD & SAN PABLO CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Contra Costa County
City Orinda
Zip Code 94563
 
Senate District
07
Assembly District 14
Congressional District 10
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Orinda Scott Christie 9252534219   schristie@cityoforinda.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$145 $-75 $70
Non-bond Funding
State/Federal*
$1,301 $-346 $954
Local**
$125 $-72 $53
Private***
$0 $0 $0
 
Total**** $1,571 $-493 $1,078

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$307 $64 $371 $370 $370 $1
Right of Way
$34 $16 $50 $56 $56 $-6
Construction
$1,230 $-573 $657 $435 $554 $103
 
Total* $1,571 $-493 $1,078 $861 $980 $98

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
08/25/2004 

03/15/2006 
 

 
08/25/2004 

03/15/2006 
100  08/25/2004 

03/15/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/13/1996 

12/30/2008 
 

 
01/31/2019 

02/05/2021 
100  11/13/1996 

05/05/2022 
270 

-15 
Begin Right of Way Phase

End Right of Way Phase
09/30/2008 

09/30/2009 
 

 
01/15/2021 

07/30/2021 
100  04/21/2021 

02/23/2022 
-3 

-7 
Begin Construction Phase

End Construction Phase
09/30/2010 

09/30/2013 
 

 
08/30/2021 

09/30/2022 
98  05/05/2022 

01/31/2024 
-8 

-16 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

03/30/2023 
02/01/2024 

04/30/2024 


-13 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.