Bridge No. 28C0331 - BEAR CREEK RD & SAN PABLO CREEK |
Description: Bridge No. 28C0331 - BEAR CREEK RD & SAN PABLO CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Contra Costa County |
City | Orinda |
Zip Code | 94563 |
Senate District |
07 |
Assembly District | 14 |
Congressional District | 10 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Orinda | Scott Christie | 9252534219 | schristie@cityoforinda.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$12 | $82 | $94 | ||||
Non-bond Funding | |||||||
State/Federal* |
$182 | $1,199 | $1,381 | ||||
Local** |
$85 | $-0 | $85 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $279 | $1,281 | $1,559 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$88 | $649 | $737 | $582 | $582 | $155 | |
Right of Way |
$20 | $30 | $50 | $35 | $35 | $15 | |
Construction |
$170 | $602 | $772 | $595 | $710 | $62 | |
Total* | $279 | $1,281 | $1,559 | $1,212 | $1,327 | $233 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
06/01/1996 06/10/1997 |
|
06/01/1996 06/10/1997 |
100 | 06/01/1996 06/10/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/16/1996 06/30/2009 |
|
01/31/2019 02/05/2021 |
100 | 09/16/1996 05/05/2022 |
272 -15 |
Begin Right of Way Phase
End Right of Way Phase |
06/30/2009 04/30/2010 |
|
01/15/2021 07/30/2021 |
100 | 04/21/2021 02/28/2022 |
-3 -7 |
Begin Construction Phase
End Construction Phase |
09/30/2010 09/30/2013 |
|
08/30/2021 09/30/2022 |
98 | 05/05/2022 01/31/2024 |
-8 -16 |
Begin Closeout Phase
End Closeout Phase |
|
|
03/30/2023 |
0 | 02/01/2024 04/30/2024 |
0 -13 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.