Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 29C0187 - AIRPORT WAY & SAN JOAQUIN RIVER |
Description: Bridge No. 29C0187 - AIRPORT WAY & SAN JOAQUIN RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Joaquin County |
City | |
Zip Code | 95304 |
Senate District |
14 |
Assembly District | 26 |
Congressional District | 11 |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
San Joaquin County | Mahmoud Saqqa | (209) 468-8924 | msaqqa@sjgov.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$421 | $113 | $534 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,860 | $1,370 | $4,229 | ||||
Local** |
$14 | $0 | $14 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $3,295 | $1,482 | $4,777 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$125 | $0 | $125 | $125 | $125 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$3,170 | $1,482 | $4,652 | $3,533 | $3,533 | $1,119 | |
Total* | $3,295 | $1,482 | $4,777 | $3,658 | $3,658 | $1,119 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
03/05/1997 01/01/2004 |
|
03/05/1997 01/01/2004 |
0 | 03/05/1997 01/01/2004 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/01/2003 08/01/2006 |
|
01/14/2004 10/01/2006 |
0 | 01/14/2004 10/01/2006 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2007 12/30/2008 |
|
09/30/2007 12/30/2008 |
100 | 09/30/2007 12/20/2008 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
04/30/2009 01/04/2013 |
|
04/30/2009 01/04/2013 |
100 | 08/17/2009 01/04/2013 |
-4 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$420,730 |
Current Approved: |
$533,584 |
Actual Expenditures: |
$420,730 |
Status as of December 31, 2023.