Bridge No. 29C0187 - AIRPORT WAY & SAN JOAQUIN RIVER

Description: Bridge No. 29C0187 - AIRPORT WAY & SAN JOAQUIN RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin County
City
Zip Code 95304
 
Senate District
14
Assembly District 26
Congressional District 11
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
San Joaquin County Mahmoud Saqqa (209) 468-8924   msaqqa@sjgov.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$421 $113 $534
Non-bond Funding
State/Federal*
$2,860 $1,370 $4,229
Local**
$14 $0 $14
Private***
$0 $0 $0
 
Total**** $3,295 $1,482 $4,777

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$125 $0 $125 $125 $125 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,170 $1,482 $4,652 $3,533 $3,533 $1,119
 
Total* $3,295 $1,482 $4,777 $3,658 $3,658 $1,119

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
03/05/1997 

01/01/2004 
 

 
03/05/1997 

01/01/2004 
03/05/1997 

01/01/2004 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2003 

08/01/2006 
 

 
01/14/2004 

10/01/2006 
01/14/2004 

10/01/2006 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/30/2007 

12/30/2008 
 

 
09/30/2007 

12/30/2008 
100  09/30/2007 

12/20/2008 


Begin Closeout Phase

End Closeout Phase
04/30/2009 

01/04/2013 
 

 
04/30/2009 

01/04/2013 
100  08/17/2009 

01/04/2013 
-4 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$420,730
Current Approved:
$533,584
Actual Expenditures:
$420,730

 

Status as of December 31, 2023.