Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 33C0026 - HIGH ST & OAKLAND ESTUARY |
Description: Bridge No. 33C0026 - HIGH ST & OAKLAND ESTUARY - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda County |
City | Alameda |
Zip Code | 94601 |
Senate District |
09 |
Assembly District | 16 |
Congressional District | 09, 13 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Alameda County | James Chu | (510) 670-5566 | james@acpwa.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$140 | $16 | $156 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,180 | $0 | $1,180 | ||||
Local** |
$9 | $0 | $9 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,328 | $16 | $1,344 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$110 | $0 | $110 | $72 | $72 | $38 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,218 | $16 | $1,234 | $1,057 | $1,057 | $178 | |
Total* | $1,328 | $16 | $1,344 | $1,128 | $1,128 | $216 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/30/1997 06/30/1997 |
|
01/30/1997 06/30/1997 |
100 | 01/30/1997 06/30/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/30/1997 06/30/2009 |
10/15/2009 |
06/30/1997 12/01/2008 |
100 | 06/30/1997 10/22/2008 |
0 1 |
Begin Right of Way Phase
End Right of Way Phase |
03/30/2009 06/30/2009 |
10/15/2009 10/15/2009 |
03/30/2009 06/30/2009 |
100 | 07/18/2006 08/11/2006 |
32 35 |
Begin Construction Phase
End Construction Phase |
10/01/2009 04/30/2010 |
10/15/2009 10/15/2009 |
01/02/2009 12/31/2009 |
100 | 01/02/2009 08/26/2009 |
0 4 |
Begin Closeout Phase
End Closeout Phase |
07/30/2010 |
|
07/30/2010 |
100 | 09/22/2009 03/26/2019 |
10 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$139,705 |
Current Approved: |
$155,939 |
Actual Expenditures: |
$121,194 |
Status as of December 31, 2023.