Caltrans Logo

Bridge No. 33C0030 - EMBARCADERO ST & LAKE MERRITT CANAL

Description: Bridge No. 33C0030 - EMBARCADERO ST & LAKE MERRITT CANAL - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Alameda County
City Oakland
Zip Code 94612
 
Senate District
09
Assembly District 16
Congressional District 09
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Oakland Jeff Roubos (510) 238-2193   jroubos@oaklandca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$952 $745 $1,697
Non-bond Funding
State/Federal*
$7,529 $20,067 $27,596
Local**
$0 $2,148 $2,148
Private***
$0 $0 $0
 
Total**** $8,480 $22,961 $31,441

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $2,802 $2,802 $2,835 $2,835 $-34
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$8,480 $20,159 $28,639 $27,991 $28,645 $-6
 
Total* $8,480 $22,961 $31,441 $30,826 $31,480 $-40

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

05/08/1997 
 

 
 

05/08/1997 
100  05/30/1994 

06/30/1997 


-2 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

10/15/2009 
 

06/30/2010 
100  02/01/2002 

03/31/2014 


-46 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

10/15/2009 
 

12/31/2010 
100  01/01/2013 

06/30/2013 


-30 
Begin Construction Phase

End Construction Phase
09/30/2010 

02/28/2012 
10/15/2009 

10/15/2009 
06/11/2011 

12/31/2012 
95  04/02/2014 

06/30/2024 
-34 

-140 
Begin Closeout Phase

End Closeout Phase
06/30/2013 

 
 

 
06/30/2013 

 
07/01/2024 

06/30/2026 
-134 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.