Caltrans Logo

Bridge No. 33C0128 - NILES BLVD & BARTD, UP RR, & BNSF RY

Description: Bridge No. 33C0128 - NILES BLVD & BARTD, UP RR, & BNSF RY - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda County
City Fremont
Zip Code 94536
 
Senate District
10
Assembly District 20
Congressional District 15
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Fremont Hans Larsen (510) 494-4722   hlarsen@fremont.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$1,248 $-659 $589
Non-bond Funding
State/Federal*
$9,984 $2,856 $12,840
Local**
$88 $1,112 $1,200
Private***
$0 $0 $0
 
Total**** $11,320 $3,309 $14,629

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$440 $860 $1,300 $921 $1,050 $250
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$10,880 $2,449 $13,329 $13,366 $14,563 $-1,234
 
Total* $11,320 $3,309 $14,629 $14,287 $15,613 $-984

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
03/08/1994 

06/09/1999 
 

 
03/08/1994 

06/09/1999 
100  03/08/1994 

06/09/1999 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2007 

12/01/2008 
 

10/15/2009 
12/01/2007 

12/31/2009 
100  02/01/2008 

04/03/2014 
-2 

-52 
Begin Right of Way Phase

End Right of Way Phase
03/01/2008 

05/01/2008 
 

10/15/2009 
03/01/2008 

03/01/2010 
100  10/01/2010 

02/27/2014 
-31 

-49 
Begin Construction Phase

End Construction Phase
04/01/2009 

12/30/2009 
10/15/2009 

10/15/2009 
03/01/2010 

11/30/2010 
100  04/04/2014 

08/30/2019 
-50 

-106 
Begin Closeout Phase

End Closeout Phase
06/30/2010 

 
 

 
06/30/2010 

 
50  09/01/2019 

06/30/2020 
-112 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$1,247,936
Current Approved:
$589,299
Actual Expenditures:
$589,299

 

Status as of December 31, 2023.