Bridge No. 33C0128 - NILES BLVD & BARTD, UP RR, & BNSF RY |
Description: Bridge No. 33C0128 - NILES BLVD & BARTD, UP RR, & BNSF RY - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda County |
City | Fremont |
Zip Code | 94536 |
Senate District |
10 |
Assembly District | 20 |
Congressional District | 15 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Fremont | Hans Larsen | (510) 494-4722 | hlarsen@fremont.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$1,248 | $-659 | $589 | ||||
Non-bond Funding | |||||||
State/Federal* |
$9,984 | $2,856 | $12,840 | ||||
Local** |
$88 | $1,112 | $1,200 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $11,320 | $3,309 | $14,629 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$440 | $860 | $1,300 | $921 | $1,050 | $250 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$10,880 | $2,449 | $13,329 | $13,366 | $14,563 | $-1,234 | |
Total* | $11,320 | $3,309 | $14,629 | $14,287 | $15,613 | $-984 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
03/08/1994 06/09/1999 |
|
03/08/1994 06/09/1999 |
100 | 03/08/1994 06/09/1999 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/01/2007 12/01/2008 |
10/15/2009 |
12/01/2007 12/31/2009 |
100 | 02/01/2008 04/03/2014 |
-2 -52 |
Begin Right of Way Phase
End Right of Way Phase |
03/01/2008 05/01/2008 |
10/15/2009 |
03/01/2008 03/01/2010 |
100 | 10/01/2010 02/27/2014 |
-31 -49 |
Begin Construction Phase
End Construction Phase |
04/01/2009 12/30/2009 |
10/15/2009 10/15/2009 |
03/01/2010 11/30/2010 |
100 | 04/04/2014 08/30/2019 |
-50 -106 |
Begin Closeout Phase
End Closeout Phase |
06/30/2010 |
|
06/30/2010 |
50 | 09/01/2019 06/30/2020 |
-112 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$1,247,936 |
Current Approved: |
$589,299 |
Actual Expenditures: |
$589,299 |
Status as of December 31, 2023.