Bridge No. 33C0147 - FRUITVALE AVE & OAKLAND ESTUARY

Description: Bridge No. 33C0147 - FRUITVALE AVE & OAKLAND ESTUARY - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Alameda County
City Alameda, Oakland
Zip Code 94501, 94601
 
Senate District
09
Assembly District 16
Congressional District 09, 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Alameda County James Chu (510) 670-5566   james@acpwa.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$106 $-53 $53
Non-bond Funding
State/Federal*
$918 $-161 $757
Local**
$9 $0 $9
Private***
$0 $0 $0
 
Total**** $1,032 $-214 $818

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$110 $-22 $88 $101 $101 $-12
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$922 $-192 $730 $834 $834 $-104
 
Total* $1,032 $-214 $818 $935 $935 $-117

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
01/30/1997 

06/30/1997 
 

 
01/30/1997 

06/30/1997 
100  01/30/1997 

06/30/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/1997 

05/30/2010 
 

 
06/30/1997 

05/30/2010 
100  06/30/1997 

07/25/2011 


-14 
Begin Right of Way Phase

End Right of Way Phase
02/28/2010 

05/10/2010 
 

 
02/28/2010 

05/10/2010 
100  07/01/2006 

07/15/2010 
45 

-2 
Begin Construction Phase

End Construction Phase
09/30/2010 

04/30/2011 
 

 
09/30/2010 

04/30/2011 
100  07/26/2011 

06/30/2015 
-10 

-51 
Begin Closeout Phase

End Closeout Phase
07/30/2011 

 
 

 
07/30/2011 

 
100  12/31/2016 

 
-66 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.