Bridge No. 33C0147 - FRUITVALE AVE & OAKLAND ESTUARY |
Description: Bridge No. 33C0147 - FRUITVALE AVE & OAKLAND ESTUARY - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Alameda County |
City | Alameda, Oakland |
Zip Code | 94501, 94601 |
Senate District |
09 |
Assembly District | 16 |
Congressional District | 09, 13 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Alameda County | James Chu | (510) 670-5566 | james@acpwa.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$106 | $-53 | $53 | ||||
Non-bond Funding | |||||||
State/Federal* |
$918 | $-161 | $757 | ||||
Local** |
$9 | $0 | $9 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,032 | $-214 | $818 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$110 | $-22 | $88 | $101 | $101 | $-12 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$922 | $-192 | $730 | $834 | $834 | $-104 | |
Total* | $1,032 | $-214 | $818 | $935 | $935 | $-117 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/30/1997 06/30/1997 |
|
01/30/1997 06/30/1997 |
100 | 01/30/1997 06/30/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/30/1997 05/30/2010 |
|
06/30/1997 05/30/2010 |
100 | 06/30/1997 07/25/2011 |
0 -14 |
Begin Right of Way Phase
End Right of Way Phase |
02/28/2010 05/10/2010 |
|
02/28/2010 05/10/2010 |
100 | 07/01/2006 07/15/2010 |
45 -2 |
Begin Construction Phase
End Construction Phase |
09/30/2010 04/30/2011 |
|
09/30/2010 04/30/2011 |
100 | 07/26/2011 06/30/2015 |
-10 -51 |
Begin Closeout Phase
End Closeout Phase |
07/30/2011 |
|
07/30/2011 |
100 | 12/31/2016 |
-66 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.