Bridge No. 33C0180 - PARK BOULEVARD & HILLSIDE

Description: Bridge No. 33C0180 - PARK BOULEVARD & HILLSIDE - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda County
City Oakland
Zip Code 94602
 
Senate District
09
Assembly District 16
Congressional District 09
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Oakland Micheal Neary (510) 238-6659   mjneary@oaklandnet.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$78 $0 $78
Non-bond Funding
State/Federal*
$1,261 $-513 $747
Local**
$47 $20 $67
Private***
$0 $0 $0
 
Total**** $1,386 $-493 $893

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$190 $0 $190 $190 $190 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,196 $-493 $703 $696 $696 $7
 
Total* $1,386 $-493 $893 $886 $886 $7

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
05/30/1994 

06/30/1997 
 

 
05/30/1994 

06/30/1997 
100  05/30/1994 

06/30/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/1997 

04/30/2009 
 

 
09/30/1997 

06/30/2010 
100  09/30/1997 

06/30/2010 


Begin Right of Way Phase

End Right of Way Phase
 

06/30/2009 
 

 
06/30/2010 

07/31/2010 
100  06/30/2010 

07/31/2010 


Begin Construction Phase

End Construction Phase
01/31/2009 

12/31/2009 
 

 
08/17/2010 

10/31/2012 
100  08/17/2010 

03/31/2013 


-5 
Begin Closeout Phase

End Closeout Phase
06/30/2010 

02/28/2013 
 

 
10/31/2012 

02/28/2013 
100  03/31/2013 

12/31/2014 
-5 

-22 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$144,787
Current Approved:
$78,312
Actual Expenditures:
$77,756

 

Status as of December 31, 2023.