Bridge No. 33C0181 - E 14TH STREET & E 12TH STREET

Description: Bridge No. 33C0181 - E 14TH STREET & E 12TH STREET - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda County
City Oakland
Zip Code 94606
 
Senate District
09
Assembly District 16
Congressional District 09
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Oakland Micheal Neary (510)238-6659   mjneary@oaklandnet.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$484 $-484 $0
Non-bond Funding
State/Federal*
$3,736 $-3,736 $0
Local**
$499 $-499 $0
Private***
$0 $0 $0
 
Total**** $4,719 $-4,719 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$4,719 $-4,719 $0 $4,603 $0 $0
 
Total* $4,719 $-4,719 $0 $4,603 $0 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/10/2004 

12/15/2004 
 

 
04/10/2004 

12/15/2004 
100  04/10/2004 

12/15/2004 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/15/2005 

09/30/2008 
 

10/15/2009 
01/15/2005 

12/31/2008 
100  01/15/2005 

12/31/2008 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/30/2010 

09/30/2012 
 

 
09/30/2010 

09/30/2012 
75  05/05/2010 

09/30/2012 


Begin Closeout Phase

End Closeout Phase
12/31/2012 

 
 

 
12/31/2012 

 
10/01/2012 

12/31/2012 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.