Bridge No. 33C0182 - E 12TH STREET & E 14TH STREET |
Description: Bridge No. 33C0182 - E 12TH STREET & E 14TH STREET - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda County |
City | Oakland |
Zip Code | 94612 |
Senate District |
09 |
Assembly District | 16 |
Congressional District | 09 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Oakland | Micheal Neary | (510) 238-6659 | mjneary@oaklandnet.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$1,219 | $-1,219 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$9,411 | $-9,411 | $0 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $10,630 | $-10,630 | $0 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$10,630 | $-10,630 | $0 | $4,603 | $0 | $0 | |
Total* | $10,630 | $-10,630 | $0 | $4,603 | $0 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
04/10/2004 12/15/2004 |
|
04/10/2004 12/15/2004 |
100 | 04/10/2004 12/15/2004 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/15/2005 09/30/2008 |
10/15/2009 |
01/15/2005 12/31/2008 |
100 | 01/15/2005 12/31/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2010 09/30/2012 |
|
09/30/2010 09/30/2012 |
75 | 05/05/2010 09/30/2012 |
5 0 |
Begin Closeout Phase
End Closeout Phase |
12/31/2012 |
|
12/31/2012 |
0 | 10/01/2012 12/31/2012 |
3 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.