Bridge No. 33C0215 - LEIMERT BLVD & SAUSAL CREEK

Description: Bridge No. 33C0215 - LEIMERT BLVD & SAUSAL CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Alameda County
City Oakland
Zip Code 94602
 
Senate District
09
Assembly District 16
Congressional District 09
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Oakland Mustafa Humran (510) 238-2954   mhumran@oaklandca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$145 $299 $444
Non-bond Funding
State/Federal*
$1,118 $4,042 $5,160
Local**
$0 $224 $224
Private***
$0 $0 $0
 
Total**** $1,262 $4,566 $5,828

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $1,473 $1,473 $1,473 $1,473 $0
Right of Way
$0 $115 $115 $115 $115 $0
Construction
$1,262 $2,978 $4,240 $1,119 $6,963 $-2,723
 
Total* $1,262 $4,566 $5,828 $2,707 $8,551 $-2,723

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
05/30/1994 

06/30/1997 
 

 
05/30/1994 

06/30/1997 
100  03/23/2015 

02/28/2017 
-253 

-239 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/30/1998 

09/30/2009 
 

 
05/31/2016 

02/28/2021 
100  03/01/2017 

01/30/2021 
-9 

Begin Right of Way Phase

End Right of Way Phase
 

11/30/2009 
 

 
05/31/2019 

12/31/2020 
100  05/29/2019 

07/30/2021 


-7 
Begin Construction Phase

End Construction Phase
01/31/2009 

12/31/2009 
 

 
04/30/2021 

11/30/2022 
15  06/28/2022 

12/31/2027 
-14 

-62 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

06/30/2023 
01/01/2028 

12/30/2028 


-67 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.