Bridge No. 33C0215 - LEIMERT BLVD & SAUSAL CREEK |
Description: Bridge No. 33C0215 - LEIMERT BLVD & SAUSAL CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Alameda County |
City | Oakland |
Zip Code | 94602 |
Senate District |
09 |
Assembly District | 16 |
Congressional District | 09 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Oakland | Mustafa Humran | (510) 238-2954 | mhumran@oaklandca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$145 | $299 | $444 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,118 | $4,042 | $5,160 | ||||
Local** |
$0 | $224 | $224 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,262 | $4,566 | $5,828 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $1,473 | $1,473 | $1,473 | $1,473 | $0 | |
Right of Way |
$0 | $115 | $115 | $115 | $115 | $0 | |
Construction |
$1,262 | $2,978 | $4,240 | $1,119 | $6,963 | $-2,723 | |
Total* | $1,262 | $4,566 | $5,828 | $2,707 | $8,551 | $-2,723 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
05/30/1994 06/30/1997 |
|
05/30/1994 06/30/1997 |
100 | 03/23/2015 02/28/2017 |
-253 -239 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/30/1998 09/30/2009 |
|
05/31/2016 02/28/2021 |
100 | 03/01/2017 01/30/2021 |
-9 1 |
Begin Right of Way Phase
End Right of Way Phase |
11/30/2009 |
|
05/31/2019 12/31/2020 |
100 | 05/29/2019 07/30/2021 |
0 -7 |
Begin Construction Phase
End Construction Phase |
01/31/2009 12/31/2009 |
|
04/30/2021 11/30/2022 |
15 | 06/28/2022 12/31/2027 |
-14 -62 |
Begin Closeout Phase
End Closeout Phase |
|
|
06/30/2023 |
0 | 01/01/2028 12/30/2028 |
0 -67 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.