Bridge No. 33C0223 - WHIPPLE ROAD & BARTD

Description: Bridge No. 33C0223 - WHIPPLE ROAD & BARTD - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda County
City Union City
Zip Code 94587
 
Senate District
10
Assembly District 18
Congressional District 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Union City Michael Renk (510) 675-5303   mrenk@ci.union-city.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$75 $25 $100
Non-bond Funding
State/Federal*
$702 $196 $898
Local**
$16 $2 $18
Private***
$0 $0 $0
 
Total**** $793 $223 $1,016

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$140 $0 $140 $140 $140 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$653 $223 $876 $826 $826 $50
 
Total* $793 $223 $1,016 $966 $966 $50

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

04/07/2009 
 

 
 

04/07/2009 
100   

04/07/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/30/2008 

05/30/2009 
 

10/15/2009 
01/30/2008 

01/30/2010 
100  07/21/2008 

10/29/2010 
-6 

-9 
Begin Right of Way Phase

End Right of Way Phase
10/30/2008 

05/30/2009 
 

10/15/2009 
10/30/2008 

01/29/2010 
100  07/07/2008 

03/01/2011 


-13 
Begin Construction Phase

End Construction Phase
09/30/2010 

10/31/2011 
10/15/2009 

 
03/01/2010 

10/31/2011 
100  02/01/2012 

04/15/2013 
-23 

-18 
Begin Closeout Phase

End Closeout Phase
10/31/2012 

 
 

 
10/31/2012 

 
100  04/15/2013 

10/15/2013 
-6 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$74,899
Current Approved:
$100,291
Actual Expenditures:
$94,607

 

Status as of December 31, 2023.