Bridge No. 33C0230 - BALLENA BLVD & BALLENA BAY

Description: Bridge No. 33C0230 - BALLENA BLVD & BALLENA BAY - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda County
City Alameda
Zip Code 94501
 
Senate District
09
Assembly District 16
Congressional District 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Alameda James Chu 510-670-5566   James@acpwa.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$66 $0 $66
Non-bond Funding
State/Federal*
$775 $36 $812
Local**
$62 $-62 $0
Private***
$0 $0 $0
 
Total**** $903 $-26 $877

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$62 $36 $98 $123 $123 $-25
Right of Way
$23 $0 $23 $0 $0 $23
Construction
$818 $-62 $756 $543 $543 $213
 
Total* $903 $-26 $877 $666 $666 $211

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

 
 

 
 

 
100  10/15/1996 

10/16/1996 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

10/15/2009 
 

05/14/2007 
100  10/17/1996 

05/14/2007 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

10/15/2009 
 

05/16/2007 
100  05/15/2007 

05/16/2007 


Begin Construction Phase

End Construction Phase
09/30/2007 

10/30/2008 
10/15/2009 

10/15/2009 
05/15/2007 

11/20/2007 
100  05/18/2007 

11/20/2007 


Begin Closeout Phase

End Closeout Phase
04/01/2009 

 
 

 
04/01/2009 

 
100  04/15/2009 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$89,466
Current Approved:
$65,605
Actual Expenditures:
$62,309

 

Status as of December 31, 2023.