Bridge No. 33C0230 - BALLENA BLVD & BALLENA BAY |
Description: Bridge No. 33C0230 - BALLENA BLVD & BALLENA BAY - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda County |
City | Alameda |
Zip Code | 94501 |
Senate District |
09 |
Assembly District | 16 |
Congressional District | 13 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Alameda | James Chu | 510-670-5566 | James@acpwa.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$66 | $0 | $66 | ||||
Non-bond Funding | |||||||
State/Federal* |
$775 | $36 | $812 | ||||
Local** |
$62 | $-62 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $903 | $-26 | $877 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$62 | $36 | $98 | $123 | $123 | $-25 | |
Right of Way |
$23 | $0 | $23 | $0 | $0 | $23 | |
Construction |
$818 | $-62 | $756 | $543 | $543 | $213 | |
Total* | $903 | $-26 | $877 | $666 | $666 | $211 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
|
|
|
100 | 10/15/1996 10/16/1996 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
10/15/2009 |
05/14/2007 |
100 | 10/17/1996 05/14/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
10/15/2009 |
05/16/2007 |
100 | 05/15/2007 05/16/2007 |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2007 10/30/2008 |
10/15/2009 10/15/2009 |
05/15/2007 11/20/2007 |
100 | 05/18/2007 11/20/2007 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
04/01/2009 |
|
04/01/2009 |
100 | 04/15/2009 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$89,466 |
Current Approved: |
$65,605 |
Actual Expenditures: |
$62,309 |
Status as of December 31, 2023.