Bridge No. 33C0237 - ELGIN ST & ASHLAND AVE

Description: Bridge No. 33C0237 - ELGIN ST & ASHLAND AVE - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda County
City Ashland
Zip Code 94580
 
Senate District
10
Assembly District 18
Congressional District 09
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Alameda County James Chu (510) 670-5566   james@acpwa.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$15 $-3 $13
Non-bond Funding
State/Federal*
$191 $-19 $172
Local**
$1 $0 $1
Private***
$0 $0 $0
 
Total**** $207 $-22 $185

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$75 $0 $75 $72 $72 $3
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$132 $-22 $110 $94 $94 $16
 
Total* $207 $-22 $185 $166 $166 $19

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
01/30/1997 

06/30/1997 
 

 
01/30/1997 

06/30/1997 
100  01/30/1997 

06/30/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/1997 

05/30/2011 
 

 
06/30/1997 

05/30/2011 
100  06/30/1997 

12/14/2010 


Begin Right of Way Phase

End Right of Way Phase
02/28/2011 

05/30/2011 
 

 
02/28/2011 

05/30/2011 
100  07/01/2006 

07/15/2010 
57 

11 
Begin Construction Phase

End Construction Phase
09/30/2011 

12/30/2011 
 

 
09/30/2011 

12/30/2011 
100  12/15/2010 

09/30/2011 
10 

Begin Closeout Phase

End Closeout Phase
03/30/2012 

 
 

 
03/30/2012 

 
100  10/01/2011 

03/26/2019 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$15,140
Current Approved:
$12,617
Actual Expenditures:
$8,819

 

Status as of December 31, 2023.