Bridge No. 33C0238 - CAMPUS DR & LION CREEK TRIBUTARY

Description: Bridge No. 33C0238 - CAMPUS DR & LION CREEK TRIBUTARY - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda County
City Oakland
Zip Code 94619
 
Senate District
09
Assembly District 16
Congressional District 09
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Oakland Micheal Neary (510) 238-6659   mjneary@oaklandnet.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$346 $0 $346
Non-bond Funding
State/Federal*
$3,029 $-1,628 $1,401
Local**
$150 $100 $250
Private***
$0 $0 $0
 
Total**** $3,525 $-1,528 $1,997

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$512 $0 $512 $510 $510 $2
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,012 $-1,528 $1,485 $1,060 $1,060 $425
 
Total* $3,525 $-1,528 $1,997 $1,570 $1,570 $427

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
05/30/1994 

06/30/1997 
 

 
05/30/1994 

06/30/1997 
100  05/30/1994 

06/30/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/30/1997 

04/30/2009 
 

 
10/30/1997 

02/28/2011 
100  10/30/1997 

02/28/2011 


Begin Right of Way Phase

End Right of Way Phase
 

06/30/2009 
 

 
02/28/2011 

03/23/2011 
100  02/28/2011 

03/23/2011 


Begin Construction Phase

End Construction Phase
01/31/2009 

12/31/2009 
 

 
04/19/2011 

12/31/2012 
100  04/19/2011 

06/30/2015 


-30 
Begin Closeout Phase

End Closeout Phase
01/01/2010 

 
 

 
01/01/2013 

05/31/2013 
100  07/01/2015 

09/30/2015 
-30 

-28 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$134,649
Current Approved:
$134,649
Actual Expenditures:
$113,072

 

Status as of December 31, 2023.