Bridge No. 33C0253 - COLISEUM WAY & DAMON SLOUGH

Description: Bridge No. 33C0253 - COLISEUM WAY & DAMON SLOUGH - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda County
City Oakland
Zip Code 94621
 
Senate District
09
Assembly District 16
Congressional District 09
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Oakland Micheal Neary (510) 238-6659   mjneary@oaklandnet.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$346 $174 $520
Non-bond Funding
State/Federal*
$2,667 $1,706 $4,373
Local**
$0 $276 $276
Private***
$0 $0 $0
 
Total**** $3,012 $2,156 $5,169

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $510 $510 $510 $510 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,012 $1,646 $4,658 $4,462 $4,462 $197
 
Total* $3,012 $2,156 $5,169 $4,972 $4,972 $197

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
05/30/1994 

06/30/1997 
 

 
05/30/1994 

06/30/1997 
100  05/30/1994 

06/30/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/30/1998 

03/31/2011 
 

 
07/31/1998 

03/31/2011 
100  07/30/1998 

03/31/2011 


Begin Right of Way Phase

End Right of Way Phase
03/31/2011 

06/29/2011 
 

 
03/31/2011 

06/29/2011 
100  03/31/2011 

06/29/2011 


Begin Construction Phase

End Construction Phase
01/31/2009 

12/31/2009 
 

10/15/2009 
07/13/2011 

12/31/2013 
100  07/13/2011 

09/16/2014 


-9 
Begin Closeout Phase

End Closeout Phase
06/30/2010 

 
 

 
12/31/2013 

05/31/2014 
100  09/17/2014 

12/31/2014 
-9 

-7 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$345,533
Current Approved:
$519,589
Actual Expenditures:
$497,029

 

Status as of December 31, 2023.