Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 34C0051 - QUINT ST & CALTRAIN & UP RR |
Description: Bridge No. 34C0051 - QUINT ST & CALTRAIN & UP RR - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Francisco |
City | San Francisco |
Zip Code | 94124 |
Senate District |
03 |
Assembly District | 13 |
Congressional District | 08 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Peninsula Joint Powers Board | Rafael Bolon | 650-622-7805 | bolonr@samtrans.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$341 | $0 | $341 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,636 | $0 | $2,636 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $2,977 | $0 | $2,977 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$2,977 | $0 | $2,977 | $0 | $2,977 | $0 | |
Total* | $2,977 | $0 | $2,977 | $0 | $2,977 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/15/2000 08/31/2001 |
|
09/15/2000 08/31/2001 |
100 | 09/15/2000 08/31/2001 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/19/2007 12/31/2008 |
10/15/2009 |
10/19/2007 12/31/2010 |
100 | 10/19/2007 04/30/2015 |
0 -53 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2009 09/30/2011 |
10/15/2009 10/15/2009 |
07/01/2011 12/31/2012 |
100 | 11/01/2015 12/31/2016 |
-53 -49 |
Begin Closeout Phase
End Closeout Phase |
03/30/2012 |
|
03/30/2012 |
0 | 12/31/2016 06/30/2017 |
-58 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.