Caltrans Logo

Bridge No. 34C0052 - JERROLD AVE & CALTRAIN & UP RR

Description: Bridge No. 34C0052 - JERROLD AVE & CALTRAIN & UP RR - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City San Francisco
Zip Code 94124
 
Senate District
03
Assembly District 13
Congressional District 08
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Peninsula Joint Powers Board Joel Slavit (650) 508-6476   slavitj@samtrans.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$184 $-184 $0
Non-bond Funding
State/Federal*
$1,419 $-1,419 $0
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $1,603 $-1,603 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,603 $-1,603 $0 $0 $341 $-341
 
Total* $1,603 $-1,603 $0 $0 $341 $-341

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/15/2000 

08/31/2001 
 

 
09/15/2000 

08/31/2001 
100  09/15/2000 

08/31/2001 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/19/2007 

12/31/2008 
 

10/15/2009 
10/19/2007 

12/31/2008 
95  10/19/2007 

01/31/2010 


-13 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/30/2009 

09/30/2011 
10/15/2009 

10/15/2009 
09/30/2009 

09/30/2011 
07/01/2010 

06/30/2011 
-9 

Begin Closeout Phase

End Closeout Phase
03/30/2012 

 
 

 
03/30/2012 

 
10/31/2011 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.