Bridge No. 34U0003 - RAMPS ON EAST SIDE OF YERBA BUENA ISLAND TUNNEL AT SFOBB ON/OFF OF I-80

Description: Bridge No. 34U0003 - RAMPS ON EAST SIDE OF YERBA BUENA ISLAND TUNNEL AT SFOBB ON/OFF OF I-80. Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Francisco County
City San Francisco
Zip Code 94130
 
Senate District
03
Assembly District 13
Congressional District 08
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
San Francisco County Transportation Authority Lily Yu 415-522-4811   lily.yu@sfcta.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$18,000 $-6,722 $11,278
Non-bond Funding
State/Federal*
$156,931 $-48,664 $108,267
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $174,931 $-55,386 $119,546

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $6,253 $6,253 $17,618 $18,163 $-11,910
Right of Way
$0 $4,744 $4,744 $5,100 $5,100 $-356
Construction
$174,931 $-66,383 $108,548 $117,527 $121,413 $-12,865
 
Total* $174,931 $-55,386 $119,546 $140,246 $144,676 $-25,131

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

 
 

 
 

09/30/2011 
100  06/01/2008 

09/30/2011 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

02/01/2012 
100  07/01/2010 

04/30/2020 


-100 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

10/15/2009 
 

02/01/2012 
97  04/01/2011 

06/30/2024 


-151 
Begin Construction Phase

End Construction Phase
09/30/2012 

 
 

01/19/2017 
12/17/2013 

08/31/2018 
99  05/01/2020 

06/30/2024 
-78 

-71 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
01/01/2024 

12/31/2024 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.