Bridge No. 35C0091 - EAST POPLAR AVE & CALTRAIN & UP RR |
Description: Bridge No. 35C0091 - EAST POPLAR AVE & CALTRAIN & UP RR - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | San Mateo |
Zip Code | 94401 |
Senate District |
08 |
Assembly District | 19 |
Congressional District | 12 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Peninsula Joint Powers Board | Rafael Bolon | (650) 622-7805 | bolonr@samtrans.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$189 | $-13 | $176 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,455 | $-99 | $1,357 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,644 | $-112 | $1,532 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,644 | $-112 | $1,532 | $1,049 | $1,049 | $484 | |
Total* | $1,644 | $-112 | $1,532 | $1,049 | $1,049 | $484 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/15/2000 08/31/2001 |
|
09/15/2000 08/31/2001 |
100 | 09/12/2000 08/31/2001 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/25/2006 12/31/2008 |
10/15/2009 |
04/25/2006 09/30/2009 |
100 | 04/25/2006 09/30/2009 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2009 09/30/2011 |
10/15/2009 10/15/2009 |
04/01/2010 03/31/2011 |
100 | 10/07/2010 12/31/2011 |
-6 -9 |
Begin Closeout Phase
End Closeout Phase |
03/30/2012 |
|
07/31/2011 |
100 | 03/30/2012 06/30/2013 |
-8 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.