Bridge No. 35C0133 - DEPARTING FLT TRFC & ARRIVING FLIGHT TRAFFIC

Description: Bridge No. 35C0133 - DEPARTING FLT TRFC & ARRIVING FLIGHT TRAFFIC - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City San Francisco
Zip Code 94128
 
Senate District
08
Assembly District 19
Congressional District 12
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
San Francisco International Airport Mike McCarron (650) 821-4000   Mike.McCarron@flysfo.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$2,731 $-743 $1,989
Non-bond Funding
State/Federal*
$21,284 $-5,656 $15,628
Local**
$2,310 $0 $2,310
Private***
$0 $0 $0
 
Total**** $26,326 $-6,399 $19,927

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$300 $0 $300 $300 $300 $0
Right of Way
$50 $-10 $40 $0 $0 $40
Construction
$25,976 $-6,389 $19,587 $13,813 $13,813 $5,774
 
Total* $26,326 $-6,399 $19,927 $14,113 $14,113 $5,814

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

04/30/1998 
 

 
 

04/30/1998 
100  01/01/1998 

04/30/1998 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

08/30/2008 
 

 
 

08/30/2008 
100  01/01/2008 

08/30/2008 


Begin Right of Way Phase

End Right of Way Phase
10/30/2008 

01/30/2009 
 

 
10/30/2008 

01/30/2009 
100  10/30/2008 

01/30/2009 


Begin Construction Phase

End Construction Phase
09/30/2010 

06/30/2012 
10/15/2009 

 
03/16/2009 

06/30/2012 
100  03/16/2009 

10/31/2011 


Begin Closeout Phase

End Closeout Phase
12/30/2012 

 
 

 
12/30/2012 

 
100  12/30/2012 

05/06/2013 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$2,731,335
Current Approved:
$2,731,335
Actual Expenditures:
$1,467,021

 

Status as of December 31, 2023.