Bridge No. 35C0133 - DEPARTING FLT TRFC & ARRIVING FLIGHT TRAFFIC |
Description: Bridge No. 35C0133 - DEPARTING FLT TRFC & ARRIVING FLIGHT TRAFFIC - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Francisco |
City | San Francisco |
Zip Code | 94128 |
Senate District |
08 |
Assembly District | 19 |
Congressional District | 12 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
San Francisco International Airport | Mike McCarron | (650) 821-4000 | Mike.McCarron@flysfo.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$2,731 | $-743 | $1,989 | ||||
Non-bond Funding | |||||||
State/Federal* |
$21,284 | $-5,656 | $15,628 | ||||
Local** |
$2,310 | $0 | $2,310 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $26,326 | $-6,399 | $19,927 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$300 | $0 | $300 | $300 | $300 | $0 | |
Right of Way |
$50 | $-10 | $40 | $0 | $0 | $40 | |
Construction |
$25,976 | $-6,389 | $19,587 | $13,813 | $13,813 | $5,774 | |
Total* | $26,326 | $-6,399 | $19,927 | $14,113 | $14,113 | $5,814 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
04/30/1998 |
|
04/30/1998 |
100 | 01/01/1998 04/30/1998 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/30/2008 |
|
08/30/2008 |
100 | 01/01/2008 08/30/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
10/30/2008 01/30/2009 |
|
10/30/2008 01/30/2009 |
100 | 10/30/2008 01/30/2009 |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2010 06/30/2012 |
10/15/2009 |
03/16/2009 06/30/2012 |
100 | 03/16/2009 10/31/2011 |
0 8 |
Begin Closeout Phase
End Closeout Phase |
12/30/2012 |
|
12/30/2012 |
100 | 12/30/2012 05/06/2013 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$2,731,335 |
Current Approved: |
$2,731,335 |
Actual Expenditures: |
$1,467,021 |
Status as of December 31, 2023.