Bridge No. 35C0161 - SPTCO & MONTE DIABLO AVE

Description: Bridge No. 35C0161 - SPTCO & MONTE DIABLO AVE - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City San Mateo
Zip Code 94401
 
Senate District
08
Assembly District 19
Congressional District 12
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Peninsula Joint Powers Board Joel Slavit (650) 508-6476   slavitj@samtrans.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$189 $-52 $136
Non-bond Funding
State/Federal*
$1,455 $-405 $1,050
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $1,644 $-458 $1,186

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,644 $-458 $1,186 $812 $812 $375
 
Total* $1,644 $-458 $1,186 $812 $812 $375

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/15/2000 

08/31/2001 
 

 
09/15/2000 

08/31/2001 
100  09/15/2000 

08/31/2001 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/25/2006 

12/31/2008 
 

10/15/2009 
04/25/2006 

09/30/2009 
100  04/25/2006 

09/30/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/30/2009 

09/30/2011 
10/15/2009 

10/15/2009 
04/01/2010 

03/31/2011 
100  10/07/2010 

12/31/2011 
-6 

-9 
Begin Closeout Phase

End Closeout Phase
03/30/2012 

 
 

 
07/31/2011 

 
100  03/30/2012 

06/30/2013 
-8 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.