Bridge No. 36C0108 - MURRAY AVE & WOODS LAGOON

Description: Bridge No. 36C0108 - MURRAY AVE & WOODS LAGOON - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Santa Cruz County
City Santa Cruz
Zip Code 95060
 
Senate District
11
Assembly District 27
Congressional District 17
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Santa Cruz Josh Spangrud 831-420-5178   jspangrud@cityofsantacruz.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$750 $532 $1,282
Non-bond Funding
State/Federal*
$6,973 $18,255 $25,227
Local**
$154 $1,822 $1,975
Private***
$0 $0 $0
 
Total**** $7,876 $20,608 $28,484

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,340 $1,282 $2,622 $2,568 $2,560 $63
Right of Way
$336 $7,328 $7,664 $13,357 $13,830 $-6,166
Construction
$6,200 $11,998 $18,198 $0 $33,137 $-14,939
 
Total* $7,876 $20,608 $28,484 $15,925 $49,526 $-21,042

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
01/01/1997 

02/01/1999 
 

 
01/01/1997 

02/01/1999 
100  01/01/1997 

02/01/1999 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/30/2000 

05/01/2009 
 

 
01/30/2000 

08/01/2021 
100  08/31/2009 

09/29/2023 
-117 

-26 
Begin Right of Way Phase

End Right of Way Phase
01/30/2008 

04/01/2009 
 

 
08/01/2011 

08/01/2021 
100  08/01/2011 

09/29/2023 


-26 
Begin Construction Phase

End Construction Phase
05/01/2009 

01/30/2011 
 

 
09/01/2021 

12/30/2024 
12/02/2024 

08/28/2026 
-40 

-20 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

02/01/2025 
08/31/2026 

12/31/2026 


-23 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.