Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 36C0108 - MURRAY AVE & WOODS LAGOON |
Description: Bridge No. 36C0108 - MURRAY AVE & WOODS LAGOON - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Santa Cruz County |
City | Santa Cruz |
Zip Code | 95060 |
Senate District |
11 |
Assembly District | 27 |
Congressional District | 17 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Santa Cruz | Josh Spangrud | 831-420-5178 | jspangrud@cityofsantacruz.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$750 | $532 | $1,282 | ||||
Non-bond Funding | |||||||
State/Federal* |
$6,973 | $18,255 | $25,227 | ||||
Local** |
$154 | $1,822 | $1,975 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $7,876 | $20,608 | $28,484 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$1,340 | $1,282 | $2,622 | $2,568 | $2,560 | $63 | |
Right of Way |
$336 | $7,328 | $7,664 | $13,357 | $13,830 | $-6,166 | |
Construction |
$6,200 | $11,998 | $18,198 | $0 | $33,137 | $-14,939 | |
Total* | $7,876 | $20,608 | $28,484 | $15,925 | $49,526 | $-21,042 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/01/1997 02/01/1999 |
|
01/01/1997 02/01/1999 |
100 | 01/01/1997 02/01/1999 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/30/2000 05/01/2009 |
|
01/30/2000 08/01/2021 |
100 | 08/31/2009 09/29/2023 |
-117 -26 |
Begin Right of Way Phase
End Right of Way Phase |
01/30/2008 04/01/2009 |
|
08/01/2011 08/01/2021 |
100 | 08/01/2011 09/29/2023 |
0 -26 |
Begin Construction Phase
End Construction Phase |
05/01/2009 01/30/2011 |
|
09/01/2021 12/30/2024 |
0 | 12/02/2024 08/28/2026 |
-40 -20 |
Begin Closeout Phase
End Closeout Phase |
|
|
02/01/2025 |
0 | 08/31/2026 12/31/2026 |
0 -23 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.