Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 37C0159 - ALAMITOS RD & ALAMITOS CREEK |
Description: Bridge No. 37C0159 - ALAMITOS RD & ALAMITOS CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Clara County |
City | |
Zip Code | 95033, 95120 |
Senate District |
15 |
Assembly District | 21 |
Congressional District | 16 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Santa Clara County | Amir Douraghy | (408) 573-2496 | amir.douraghy@rda@sccgov.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$791 | $-791 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$6,772 | $-6,772 | $0 | ||||
Local** |
$167 | $-167 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $7,730 | $-7,730 | $0 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$775 | $-775 | $0 | $660 | $0 | $0 | |
Right of Way |
$60 | $-60 | $0 | $0 | $0 | $0 | |
Construction |
$6,895 | $-6,895 | $0 | $0 | $0 | $0 | |
Total* | $7,730 | $-7,730 | $0 | $660 | $0 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
12/30/2001 02/28/2002 |
|
12/30/2001 02/28/2002 |
100 | 12/30/2001 02/28/2002 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/30/2008 12/30/2010 |
10/15/2009 |
03/30/2008 12/30/2011 |
35 | 04/28/2009 02/28/2013 |
-13 -14 |
Begin Right of Way Phase
End Right of Way Phase |
12/30/2009 12/30/2010 |
|
12/30/2009 12/30/2010 |
0 | 11/23/2012 01/03/2013 |
-35 -24 |
Begin Construction Phase
End Construction Phase |
03/30/2011 06/30/2012 |
10/15/2009 10/15/2009 |
06/15/2012 06/15/2013 |
0 | 03/01/2013 06/30/2015 |
-9 -25 |
Begin Closeout Phase
End Closeout Phase |
12/30/2012 |
|
12/30/2012 |
0 | 07/01/2015 12/30/2015 |
-30 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.