Bridge No. 37C0159 - ALAMITOS RD & ALAMITOS CREEK

Description: Bridge No. 37C0159 - ALAMITOS RD & ALAMITOS CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Clara County
City
Zip Code 95033, 95120
 
Senate District
15
Assembly District 21
Congressional District 16
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Santa Clara County Amir Douraghy (408) 573-2496   amir.douraghy@rda@sccgov.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$791 $-791 $0
Non-bond Funding
State/Federal*
$6,772 $-6,772 $0
Local**
$167 $-167 $0
Private***
$0 $0 $0
 
Total**** $7,730 $-7,730 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$775 $-775 $0 $660 $0 $0
Right of Way
$60 $-60 $0 $0 $0 $0
Construction
$6,895 $-6,895 $0 $0 $0 $0
 
Total* $7,730 $-7,730 $0 $660 $0 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
12/30/2001 

02/28/2002 
 

 
12/30/2001 

02/28/2002 
100  12/30/2001 

02/28/2002 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/30/2008 

12/30/2010 
 

10/15/2009 
03/30/2008 

12/30/2011 
35  04/28/2009 

02/28/2013 
-13 

-14 
Begin Right of Way Phase

End Right of Way Phase
12/30/2009 

12/30/2010 
 

 
12/30/2009 

12/30/2010 
11/23/2012 

01/03/2013 
-35 

-24 
Begin Construction Phase

End Construction Phase
03/30/2011 

06/30/2012 
10/15/2009 

10/15/2009 
06/15/2012 

06/15/2013 
03/01/2013 

06/30/2015 
-9 

-25 
Begin Closeout Phase

End Closeout Phase
12/30/2012 

 
 

 
12/30/2012 

 
07/01/2015 

12/30/2015 
-30 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.