Bridge No. 37C0173 - ALDERCROFT HTS RD & LOS GATOS CREEK

Description: Bridge No. 37C0173 - ALDERCROFT HTS RD & LOS GATOS CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Clara County
City Los Gatos
Zip Code 95033
 
Senate District
15
Assembly District 21
Congressional District 15
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Santa Clara County Amir Douraghy (408) 573-2496   amir.douraghy@rda.sccgov.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$103 $0 $103
Non-bond Funding
State/Federal*
$1,337 $0 $1,337
Local**
$135 $0 $135
Private***
$0 $0 $0
 
Total**** $1,575 $0 $1,575

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$675 $0 $675 $696 $696 $-21
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$900 $0 $900 $876 $876 $24
 
Total* $1,575 $0 $1,575 $1,572 $1,572 $3

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
12/30/2001 

02/28/2002 
 

 
12/30/2001 

02/28/2002 
100  12/30/2001 

02/28/2002 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/2002 

01/30/2006 
 

 
06/30/2002 

01/30/2006 
100  06/30/2002 

01/30/2006 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/30/2007 

12/30/2007 
 

 
05/30/2007 

12/30/2007 
100  05/30/2007 

12/30/2007 


Begin Closeout Phase

End Closeout Phase
06/30/2008 

 
 

 
06/30/2008 

 
100  09/30/2010 

 
-27 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$103,230
Current Approved:
$103,230
Actual Expenditures:
$93,771

 